NOTICE DATE: April 10, 2023

NOTICE TYPE: M-B040723-02 Operations

SHORT DESCRIPTION: Update - Proposal to Add Bonilla - N Edinburgh 345 kV and Rio Hondo - South Santa Rosa - Primera 138 kV Pre-Contingency Action Plan

INTENDED AUDIENCE: All Market Participants

DAYS AFFECTED: April 14, 2023

LONG DESCRIPTION: Updated submission date to provide CMP proposals from April 21 to April 14, 2023.

ERCOT has received a proposal from EDF Renewables/RWE to add a Pre-Contingency Action Plan (PCAP) to manage the overload caused by high wind in the Rio Grand Valley where the contingency loss of Bonilla - N Edinburg 345 kV line and Rio Hondo - South Santa Rosa - Primeria 138 kV lines overloads the Burns – Rio Hondo 138 kV and La Palma – Haine 138 kV lines.

The proposed Bonilla - N Edinburgh 345 kV and Rio Hondo - South Santa Rosa - Primera 138 kV PCAP is being reviewed by ERCOT as a part of the 2023 Constraint Management Plans Annual Review.

ACTION REQUIRED: Any comments to this proposal are due to ERCOT by 5:00 pm on April 14, 2023 and should be submitted to [log in to unmask] using the attached comment form.

ADDITIONAL INFORMATION: Information regarding this proposal and all Constraint Management Plans can be found on the Market Information System (MIS) Transmission page of the Grid section under the Submitted Remedial Action Schemes (RASs) and Constraint Management Plans (CMPs) (EMIL ID NP3-614-M, Report Type ID 11419) Secure area. A Digital Certificate with the role ICE_M_VIEW_ECEII is required to access this ECEII data.

CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask].