NOTICE DATE:  September 25, 2023

NOTICE TYPE:  W-A092523-01 Operations

SHORT DESCRIPTION:  Implementation of maximum shadow price for an irresolvable constraint in SCED

INTENDED AUDIENCE:  ERCOT Market Participants

DAY AFFECTED:  September 25, 2023

LONG DESCRIPTION:  ERCOT has identified a transmission constraint that has met the criteria of being considered irresolvable on September 23, 2023, per the criteria defined in Section 3.6.1 of the business practice document, “Setting the Shadow Price Caps and Power Balance Penalties in Security Constrained Economic Dispatch.”  The update to the maximum Shadow Price will occur between 3:00 PM and 4:00 PM Central Prevailing Time (CPT) on September 25, 2023 and will become effective immediately. The updated maximum Shadow Price will remain in effect until otherwise notified through a Market Notice. The contingency/constraint pair and updated maximum shadow price (set in accordance with Section 3.6.2 of that same document) are as follows:

Contingency Name

Constraint Name

From Station/kV

Description

Maximum Shadow Price

SCARBU28

CKT_979_1

MAGPLANT /138

Loss of the 138 kV line from Cardinal Lane to Burleson Aen overloading the 138 kV line from Magnesium Plant to Northland

2,000 $/MWh

 

This new maximum shadow price will be used for all constraints in SCED sharing the same monitored element (i.e. constraint name) and direction.

 ADDITIONAL INFORMATION:  The business practice document is posted under Key Documents on the Real-Time Market webpage at http://www.ercot.com/mktinfo/rtm/.

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask].

If you are receiving email from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com

 

 

dg