NOTICE_PRR_SCR Archives

Notice_PRR_SCR

NOTICE_PRR_SCR@LISTS.ERCOT.COM

Options: Use Forum View

Use Monospaced Font
Show HTML Part by Default
Show All Mail Headers

Message: [<< First] [< Prev] [Next >] [Last >>]
Topic: [<< First] [< Prev] [Next >] [Last >>]
Author: [<< First] [< Prev] [Next >] [Last >>]

Print Reply
Subject:
From:
ERCOT Client Services <[log in to unmask]>
Date:
Fri, 29 Jul 2016 17:54:48 +0000
Content-Type:
multipart/alternative
Parts/Attachments:
text/plain (3310 bytes) , text/html (20 kB)
NOTICE DATE:  July 29, 2016

NOTICE TYPE:  M-D072916-01 NPRR

SHORT DESCRIPTION:  Implementation of NPRR662

INTENDED AUDIENCE:  ERCOT Market Participants

DAY AFFECTED:  August 30 - September 1, 2016

LONG DESCRIPTION:  ERCOT will implement Nodal Protocol Revision Request (NPRR) 662, Proxy Energy Offer Curves, between August 30 and September 1, 2016.

NPRR662 addresses proxy Energy Offer Curves generated by ERCOT for a Resource that does not submit an Energy Offer Curve or submits an incomplete Energy Offer Curve and will affect the calculation of Real-Time Average Incremental Energy Cost (RTAIEC).

For an Intermittent Renewable Resource (IRR) without an Energy Offer Curve, the monotonically increasing proxy Energy Offer Curve will be created such that the price at HSL will be $1,500 as described below:

MW

Price (per MWh)

HSL

$1,500

HSL minus 1 MW

-$249.99

LSL

-$250.00



For a Resource without a full-range Energy Offer Curve, the proxy Energy Offer Curve created will extend the offer price from last point on the submitted Energy Offer Curve to the Resource's HSL as described below:

MW

Price (per MWh)

HSL (if more than highest MW in submitted Energy Offer Curve)

Price associated with highest MW in submitted Energy Offer Curve

Energy Offer Curve

Energy Offer Curve

1 MW below lowest MW in Energy Offer Curve (if more than LSL)

-$249.99

LSL (if less than lowest MW in Energy Offer Curve)

-$250.00



For a RUC-Committed Resource that has submitted an Energy Offer Curve, the proxy Energy Offer Curve will be created as described below:

MW

Price (per MWh)

HSL (if more than highest MW in Energy Offer Curve)

Higher of $1,500 or price associated with the highest MW in QSE submitted Energy Offer Curve

Energy Offer Curve

Greater of $1,500 or the QSE submitted Energy Offer Curve

Zero

Greater of $1,500 or the first price point of the QSE submitted Energy Offer Curve



For a Controllable Load Resource without a full-range RTM Energy Bid, the proxy energy bid will be created as described below:

MW

Price (per MWh)

LPC to MPC minus maximum MW of RTM Energy Bid

Price associated with the lowest MW in submitted RTM Energy Bid curve

MPC minus maximum MW of RTM Energy Bid to MPC

RTM Energy Bid curve

MPC

Right-most point (lowest price) on RTM Energy Bid curve



New Settlement Bill Determinants:



A new factor was created for the $1,500 IRR HSL value for ease of implementation.



Bill Determinant

Short Description

Extract

Extract Table

IRRHSLPR

Renewable HSL Price

PRDE

FACTOR

FACTORVALUE



ACTION REQUIRED:  Implement changes to shadow Settlement systems for NPRR662.

ADDITIONAL INFORMATION:  Pursuant to Nodal Protocol Section 21.6, Nodal Protocol Revision Implementation, ERCOT is required to provide notice as soon as practicable, but no later than ten days prior to implementation.

NPRR662<http://www.ercot.com/mktrules/issues/NPRR662> and associated documents can be found on the ERCOT website.

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask]<mailto:[log in to unmask]>.

If you are receiving email from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.