NOTICE_RELEASE_WHOLESALE Archives

Notice Release Wholesale

NOTICE_RELEASE_WHOLESALE@LISTS.ERCOT.COM

Options: Use Forum View

Use Monospaced Font
Show HTML Part by Default
Show All Mail Headers

Message: [<< First] [< Prev] [Next >] [Last >>]
Topic: [<< First] [< Prev] [Next >] [Last >>]
Author: [<< First] [< Prev] [Next >] [Last >>]

Print Reply
Subject:
From:
ERCOT Client Services <[log in to unmask]>
Date:
Fri, 1 Sep 2017 16:22:30 +0000
Content-Type:
multipart/alternative
Parts/Attachments:
text/plain (3128 bytes) , text/html (16 kB)
***** EXTERNAL email. Please be cautious and evaluate before you click on links, open attachments, or provide credentials. *****

NOTICE DATE:  September 1, 2017

NOTICE TYPE:  M-A122016-07 Operations

SHORT DESCRIPTION:  Additional implementation details of NPRR758, Improved Transparency for Outages Potentially having a High Economic Impact (Rescheduled Outages)

INTENDED AUDIENCE:  Transmission Service Providers

DAY AFFECTED:  September 14, 2017

LONG DESCRIPTION:  ERCOT will be implementing changes to the Outage Scheduler for the remaining grey-boxed portion of Nodal Protocol Revision Request (NPRR) 758, Improved Transparency for Outages Potentially Having a High Economic Impact, on September 14, 2017.

This NPRR will:

********* Identify Outages that have historically resulted in high congestion costs, as adjusted through a stakeholder review process to account for upgrades and other changes that would affect the fidelity of this list as an indicator of Outages that might cause future congestion;

********* Encourage earlier submission of these Outages;

********* Formalize the process of rescheduling these Outages when they must be moved due to Forced Outages or later-arriving generator Outages; and

********* Provide improved transparency to Market Participants when Outages with this potential congestion impact are submitted with less than 90 days' notice.

Specific items within this NPRR include:

********* Posting of High Impact Outages (HIOs) requested 90 days or less; and

********* Introduction of a Rescheduled Outage type in the Outage Scheduler

Following are the details for the new daily Secure High Impact Outages (HIOs) report which will be posted on the Market Information System (MIS) on the Grid > Transmission page:



EMIL ID

Product Name

Report ID

NP3-154-CD

High Impact Outages - Submitted 90 Days or Less

14857



In addition, modifications to the Consolidated Transmission Outage Report (EMIL ID NP3-157-CD, Report ID 13446) will be made to include two new columns:



********* G90 Flag

********* HIO Flag

This report is available on the Market Information System (MIS) on the Grid > Transmission page.

ADDITIONAL INFORMATION:  Pursuant to Protocol Section 21.6, Nodal Protocol Revision Implementation, ERCOT is required to provide notice as soon as practicable, but no later than ten days prior to implementation.

NPRR758 and associated documents can be found on the ERCOT website, under Market Rules, at http://www.ercot.com/mktrules/issues/NPRR758.

With the implementation of NPRR758, a new Current Day Reports XSD has been posted to the ERCOT website.  The XSDs can be found on the ERCOT website at http://www.ercot.com/services/mdt/index.html.

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask]<mailto:[log in to unmask]>.