WMWG Archives

Wholesale Market Working Group

WMWG@LISTS.ERCOT.COM

Options: Use Forum View

Use Monospaced Font
Show HTML Part by Default
Show All Mail Headers

Message: [<< First] [< Prev] [Next >] [Last >>]
Topic: [<< First] [< Prev] [Next >] [Last >>]
Author: [<< First] [< Prev] [Next >] [Last >>]

Print Reply
Subject:
From:
"Mago, Nitika" <[log in to unmask]>
Reply To:
Mago, Nitika
Date:
Thu, 20 May 2021 19:57:08 +0000
Content-Type:
multipart/alternative
Parts/Attachments:
text/plain (3668 bytes) , text/html (9 kB)
***** EXTERNAL email. Please be cautious and evaluate before you click on links, open attachments, or provide credentials. *****

WMWG and PDCWG members
Forwarding the Market Notice for SCR811 that was sent yesterday.
Regards
Nitika
From: ERCOT Client Services
Sent: Wednesday, May 19, 2021 5:53 PM
To: [log in to unmask]; [log in to unmask]
Cc: Ercot Account Managers <[log in to unmask]>; Market Support Services <[log in to unmask]>
Subject: M-A051921-01 Implementation Details of SCR811, Preparing for the addition of Intra-Hour Photo Voltaic Power Forecast to Generation To Be Dispatched Calculation


NOTICE DATE: May 19, 2021

NOTICE TYPE: M-A051921-01 NPRR/SCR

SHORT DESCRIPTION: Implementation Details of SCR811, Preparing for the addition of Intra-Hour Photo Voltaic Power Forecast to Generation To Be Dispatched Calculation

INTENDED AUDIENCE: Qualified Scheduling Entities

DAYS AFFECTED: May 27, 2021

LONG DESCRIPTION:  On May 27, 2021, System Change Request (SCR) 811, Addition of Intra-Hour PhotoVoltaic Power Forecast to GTBD Calculation will be implemented.

This SCR updates the formula used by the Resource Limit Calculator to calculate the Generation To Be Dispatched (GTBD) value. The updated formula for GTBD will include the addition of the Intra-Hour PhotoVoltaic Power Forecast (IHPPF) via a calculated predicted solar ramp (PSRR) times five and a configurable factor. This addition will help Security-Constrained Economic Dispatch (SCED) take into account the anticipated 5-minute solar ramp in its 5-minute Base Points.

This change will result in the GTBD being calculated as the following:

GTBD = Total Gen + K1*10*System Load Frequency Bias + K2*[(net non-conforming Load) – (net filtered non-conforming Load)] + K3*5*PLRR + K4*Regulation Deployed - K5*ACE Integral – K6*5*PWRR – K8*5*PSRR

            |PSRR| ≤ Max PSRR Threshold

Upon implementation of SCR 811, K8 value will be set to zero and the GTBD calculation will not be impacted. ERCOT is planning to set K8 to a non-zero value starting on June 1, 2021. In preparation for this transition, ERCOT will be increasing the quantities for Regulation Up to be procured between June 1 and 3, 2021. The increase in Regulation Up quantities primarily affect HE16 through HE21 and range between 25 and 165 MW. The updated quantities of Regulation Up for these days have been posted to Ancillary Service Requirement Methodology<https://mis.ercot.com/secure/data-products/grid/forecasts?id=NP3-783-M> on the Market Information System (MIS) site. A digital certificate is required to view the report. ERCOT will communicate via a Market Notice if the specific date and time of the initial activation of K8 to a non-zero value changes prior to the activation.

ADDITIONAL INFORMATION: SCR811<http://www.ercot.com/mktrules/issues/SCR811> and associated documents can be found on the ERCOT website.

CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask]<mailto:[log in to unmask]>.

If you are receiving email from a public ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com<http://lists.ercot.com/>.



mm

########################################################################

To unsubscribe from the WMWG list, click the following link:
http://lists.ercot.com/scripts/wa-ERCOT.exe?SUBED1=WMWG&A=1

ATOM RSS1 RSS2