NOTICE
TYPE:
M-A050208-01 Operations
CLASSIFICATION:
Public
SHORT
DESCRIPTION: Implementation schedule for nodal market transition
activities
INTENDED
AUDIENCE:
All Market Participants
DAY
AFFECTED:
See below
LONG
DESCRIPTION: In accordance with Protocol Section 21.12.2, Notice to Market
Participants of Activities Essential for Nodal Market Open, ERCOT is providing
an update of the implementation schedules for the following nodal market
transition activities.
Nodal Market Design Activity |
Target Date |
Single entry
Network Model |
July 14, 2008 |
Initiation of the
168-hour testing |
September 1, 2008 |
Completion of
168-hour test |
October 1, 2008 |
First congestion
revenue rights monthly auction |
November 17, 2008 |
Real-time market
implementation |
December 1, 2008 |
Day-ahead market
implementation |
December 8, 2008 |
CONTACT: If you have any questions, please
contact your ERCOT Account Manager. You may also call the general ERCOT Client
Services phone number at (512) 248-3900 or contact ERCOT Client Services via
e-mail at [log in to unmask].