NOTICE DATE:  November 24, 2008

NOTICE TYPE:  W-A112408-01 Operations

SHORT DESCRIPTION:  ERCOT has determined the Congestion Management (CM)
Zone Shadow Price names for 2009. The ERCOT test environment will be
available for market participant year-end testing.

INTENDED AUDIENCE:  QSE Operations and Settlement Personnel

DAYS AFFECTED:  December 11 and 16, 2008 - Test Days

LONG DESCRIPTION:  ERCOT has determined the short names for the 2009
Congestion Management Zones and the recorder names for the 2009
Congestion Shadow Prices. 

The Short Names are the identifiers that Market Participants will see in
their Data Extracts designating the CM Zone in billing determinants.
These values are:

CM Zone Name

Short Name

NORTH2009

N09

HOUSTON2009

H09

SOUTH2009

S09

WEST2009

W09

 

The Shadow Price Recorder names are as follows:

 

Congestion Path Name

Recorder Name

WEST-NORTH

MCPESPC_W09N09

NORTH-WEST

MCPESPC_N09W09

SOUTH-NORTH

MCPESPC_S09N09

NORTH-SOUTH

MCPESPC_N09S09

NORTH-HOUSTON

MCPESPC_N09H09

ADDITIONAL INFORMATION:  The ERCOT Market Operations Test Environment
(MOTE) will be available for two test days on December 11 and 16, 2008
according to the schedules below. 

MOTE 2009 CM Zone Testing - Test Day #1 December 11

Real-time

Simulated time

 

12/11/08 8:00

12/31/08 17:00

Start test; Day Ahead and AS Market Open for Trade Day January 1, 2009

12/11/08 11:00

12/31/08 20:00

AS Market Close for Trade Day January 1, 2009

12/11/08 12:00

12/31/08 21:00

Day Ahead Market Close for Trade Day January 1, 2009. Run RPRS for
January 1, 2009

12/11/08 15:00

12/31/08 24:00

New Year Transition to January 1, 2009

12/11/08 18:00

1/01/09 03:00

Close of test

 

MOTE 2008 CM Zone Testing - Test Day #2 December 16

Real-time

Simulated time

 

12/16/08 8:00

12/31/08 17:00

Start test; Day Ahead and AS Market Open for Trade Day January 1, 2009

12/16/08 11:00

12/31/08 20:00

AS Market Close for Trade Day January 1, 2008

12/16/08 12:00

12/31/08 21:00

Day Ahead Market Close for Trade Day January 1, 2009. Run RPRS for
January 1, 2009.

12/16/08 15:00

12/31/08 24:00

New Year Transition to January 1, 2009

12/16/08 18:00

1/01/09 03:00

Close of test

 

ACTION REQUIRED:  ERCOT requests participants to assess the impact on
their systems and prepare accordingly. ERCOT will be conducting a
simulation test of year-end transition in the second week of December
2008. 

CONTACT:  If you have any questions, please contact your ERCOT Account
Manager. You may also call the general ERCOT Client Services phone
number at (512) 248-3900 or contact ERCOT Client Services via e-mail at
[log in to unmask]

If you are receiving e-mail from an ERCOT distribution list that you no
longer wish to receive, please follow this link in order to unsubscribe
from this list: http://lists.ercot.com <http://lists.ercot.com/> .

sg/kd