NOTICE DATE: January 20, 2010
NOTICE TYPE: W-B012010-01
Settlements
SHORT DESCRIPTION: Results of
the procurement of EILS for the February – May 2010 Contract Period
INTENDED AUDIENCE: QSE
Settlement Personnel
DAYS AFFECTED: February 1 – May 31, 2010
LONG DESCRIPTION: ERCOT has
released the results of its procurement of Emergency Interruptible Load Service
(EILS) for the Contract Period of February 1, 2010, through May 31, 2010.
Public Utility Commission (PUC) Substantive Rule 25.507 (f) requires ERCOT to
report publicly the number of MW procured per Time Period, the number of
Resources providing the service and the projected total cost of the service for
that Contract Period within 10 days of the awards for a Contract Period. ERCOT
is notifying Qualified Scheduling Entities (QSEs) of their awards and contracts
are being delivered today to QSEs whose offers were selected. Contracts are due
back at ERCOT by January 28, 2010.
The results of this procurement are as follows:
Business Hours 1 HE 0900 through 1300, Monday thru Friday
except ERCOT Holidays; 425 hours |
|
MW Procured or Self Arranged |
292.7 |
Number of EILS Resources |
67 (includes 38 aggregations) |
Projected cost |
$ 980,512.08 |
Average cost per MW per hour |
$7.88 |
Business Hours 2 HE 1400 through 1600, Monday thru Friday
except ERCOT Holidays; 255 hours |
|
MW Procured or Self Arranged |
288.1 |
Number of EILS Resources |
67 (includes 38 aggregations) |
Projected cost |
$578,364.87 |
Average cost per MW per hour |
$7.87 |
Business Hours 3 HE 1700 through 2000, Monday thru Friday
except ERCOT Holidays; 340 hours |
|
MW Procured or Self Arranged |
275.2 |
Number of EILS Resources |
67 (includes 38 aggregations) |
Projected cost |
$794,386.68 |
Average cost per MW per hour |
$8.49 |
Non-Business Hours All other hours; 1,859 hours |
|
MW Procured or Self Arranged |
246.7 |
Number of EILS Resources |
61 (includes 35 aggregations) |
Projected cost |
$3,447,842.73 |
Average cost per MW per hour |
$7.52 |
Total projected cost of EILS for this Contract Period,
including projected credits for EILS Self-Provision, is $5,801,106.36.
This is the first EILS procurement for the 2010 program
year. The final 2009 program year cost of EILS, including projected credits for
EILS Self-Provision, will not exceed $18,130,594.14. The cost of EILS is capped
at $50 million per year pursuant to PUC Substantive Rule §25.507(b)(3).
CONTACT: If you have specific
questions about the EILS program, please send an email to [log in to unmask]. If you have any other
questions, please contact your ERCOT Account Manager. You may also call the
general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT
Client Services via email at [log in to unmask].
If you
are receiving email from an ERCOT distribution list that you no longer wish to
receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.
dh