NOTICE DATE: May 26, 2010
NOTICE TYPE: W-A052610-01 Operations
SHORT DESCRIPTION: Implementation Reminder for
PRR841, Revise Total ERCOT Wind Power Forecast (TEWPF)
INTENDED AUDIENCE: QSEs Representing WGRs
DAY AFFECTED: April 1, 2010
LONG DESCRIPTION: Protocol Revision Request (PRR)
841, Revise Total ERCOT Wind Power Forecast (TEWPF), was effective on April 1,
2010. This PRR amended ERCOT Protocol Section 4.4.15, QSE Resource Plans, to
require that Qualified Scheduling Entities (QSEs) representing Wind-powered
Generation Resources (WGRs) use ERCOT-provided Short-Term Wind Power Forecasts
(STWPFs) for WGRs as the planned operating level in their Resource Plans. This
is required for the Resource Plan submitted for 16:00 in the Day Ahead and
prior to the Replacement Reserve Service (RPRS) Market running in the
Adjustment Period.
The STWPF is a fifty percent (50%) probability of exceedance
forecast of the generation in MWh per hour from each WGR. Prior to April 1,
2010, QSEs were required to use an eighty percent (80%) probability of
exceedance forecast; however, this was changed as part of PRR841.
ACTION REQUIRED: QSEs representing WGRs should
ensure that they are now using the ERCOT-provided STWPF as required by ERCOT
Protocol Section 4.4.15, QSE Resource Plans.
ADDITIONAL INFORMATION: PRR841
may be found at the following link:
http://www.ercot.com/mktrules/issues/prr/825-849/841/index.
CONTACT: If you have any questions, please
contact your ERCOT Account Manager. You may also call the general ERCOT Client
Services phone number at (512) 248-3900 or contact ERCOT Client Services via
email at [log in to unmask].
If you are receiving email from an ERCOT
distribution list that you no longer wish to receive, please follow this link
in order to unsubscribe from this list: http://lists.ercot.com.
ad