*******TEXAS NODAL MARKET
NOTICE*******
NOTICE DATE: August 23,
2010
NOTICE TYPE: Market
Trials
SHORT DESCRIPTION: REMINDER
– The 40-Hour Full-System Market and
Reliability Test is scheduled to take place beginning on August 26, 2010
INTENDED AUDIENCE: Qualified
Scheduling Entities, QSEs with Resources, Resource Entities, Nodal Accountable
Executives, Nodal Transition Project Managers, Market Trial Contacts
DAYS AFFECTED: August 26
– 28, 2010
LONG DESCRIPTION:
The 40-Hour Test is scheduled to take place beginning August
26, 2010, at 10:00 CDT and ending August 28, 2010, at 02:00 CDT. Participants should take the
following steps:
ACTION REQUIRED: Please
advise operators and other personnel performing Zonal market activities that
the necessary support staff will need to be available beginning 08:00 CDT on
August 26, 2010, and ending 02:00 CDT on August 28, 2010, to support this
testing.
CONTACT: If you have any
questions, please contact either the Market Trials team by email at [log in to unmask] or your ERCOT
Account Manager. You may also call the general ERCOT Client Services phone
number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask].