*******TEXAS NODAL MARKET
NOTICE*******
NOTICE DATE: August 26,
2010
NOTICE TYPE: Market
Trials
SHORT DESCRIPTION: REMINDER
– The 40-Hour Full-System Market and
Reliability Test is scheduled to start today, August 26, 2010, at 10:00 CDT
INTENDED AUDIENCE:
Qualified Scheduling Entities, QSEs with Resources, Resource Entities, Nodal
Accountable Executives, Nodal Transition Project Managers, Market Trial
Contacts
DAYS AFFECTED: August 26
– 28, 2010
LONG DESCRIPTION:
The 40-Hour
Full-System Market and Reliability Test is scheduled to start
today, August 26, 2010, beginning at 10:00 CDT. The
test is scheduled to run until 02:00 CDT on August 28, 2010.
Market participants should take the following steps:
During
the transition from Zonal to Nodal control and from Nodal to Zonal, each
participating QSE will receive an individual call from the ERCOT Operator
instructing them to switch control from one system to the other. QSEs must not switch to Nodal control until instructed to do so
by ERCOT through this call.
ACTION REQUIRED: Please
advise operators and other personnel performing Zonal market activities that
the necessary support staff will need to be available to support this testing
through 02:00 CDT on August 28, 2010.
CONTACT: If you
have any questions, please contact either the Market Trials team by email at [log in to unmask] or your ERCOT
Account Manager. You may also call the general ERCOT Client Services phone
number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask].