*******TEXAS NODAL MARKET
NOTICE*******
NOTICE DATE: August 2,
2010
NOTICE TYPE: Market
Trials
SHORT DESCRIPTION: The 24-Hour Full-System Market and Reliability Test is scheduled to take place on
August 4 – 5, 2010
INTENDED AUDIENCE:
Qualified Scheduling Entities, QSEs with Resources, Resource Entities, Nodal Accountable
Executives, Nodal Transition Project Managers, Market Trial Contacts
DAYS AFFECTED: August 4
– 5, 2010
LONG DESCRIPTION:
The 24-Hour Test is scheduled to take place beginning August
4, 2010, at 12:00 CDT and ending August 5, 2010, at 12:00 CDT. Participants should take the
following steps:
ACTION REQUIRED: Please
advise operators and other personnel performing Zonal market activities that
the necessary support staff will need to be available beginning 08:00 CDT on
August 4 and ending 12:00 CDT on August 5, 2010, to support this testing.
CONTACT: If you have any
questions, please contact either the Market Trials team by email at [log in to unmask] or your ERCOT
Account Manager. You may also call the general ERCOT Client Services phone
number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask].
If you
are receiving email from an ERCOT distribution list that you no longer wish to
receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.
dh