NOTICE
DATE:
November 11, 2010
NOTICE
TYPE: M-A102710-02 Operations
SHORT
DESCRIPTION: REMINDER
– TSPs to submit their equipment rating
methodologies before November 15, 2010
INTENDED
AUDIENCE:
Transmission Service Providers (TSPs)
DAY
AFFECTED: Ratings
to be submitted before November 15, 2010
LONG DESCRIPTION: This Notice
is a reminder for TSPs to submit their rating methodologies, in accordance with
Nodal Protocol Section 3.10 (3), before November 15, 2010, to be posted to the
Market Information System (MIS) for Nodal Go-Live. All methodologies will be
posted under the TSP Rating Methodology link at https://mis.ercot.com/pps/tibco/mis/Pages/Grid+Information/Long+Term+Planning.
ACTION REQUIRED: If you
have not already done so, TSPs shall submit any needed equipment rating
methodologies as an attachment to a Special Action Model Request (SAMR) into
the Network Model Management System (NMMS). The naming convention for the SAMR
should be “TSPNAME Rating Methodology xx/xx/2010.”
ADDITIONAL INFORMATION: TSPs are also required to provide future
updates to their methodology documents if those methodologies change. The
process for updating the documents will be the same as the initial posting. The
updated document should be attached to a SAMR and submitted to ERCOT. ERCOT
will post the updated documents within seven days of receipt. Updates to the
rating methodology documents are necessary only if the document changes or if
ERCOT requests more detailed information.
The following Protocol section is
provided for reference:
3.10 Network
Operations Modeling and Telemetry
(3) TSPs
and Resource Entities shall provide ERCOT with equipment ratings and update the
ratings as required by ERCOT. ERCOT shall post all equipment ratings on the
Market Information System (MIS) Secure Area no later than the day prior to the
ratings becoming effective including the identity of the Transmission Element,
old rating and new rating, effective date, and a text reason supplied by the
appropriate TSPs and Resource Entities for the rating change. ERCOT may request
TSPs and Resource Entities to provide detailed information on the methodology,
including data for determination of each requested rating. ERCOT may review and
comment on the methodology. ERCOT shall post all methodologies on the MIS
Secure Area within seven days following a change in methodology.
CONTACT: If you have any questions, please contact [log in to unmask] or your ERCOT Account Manager. You may also call the
general ERCOT Client Services phone number at (512) 248-3900
or contact ERCOT Client Relations via email at [log in to unmask].
If you
are receiving email from an ERCOT distribution list that you no longer wish to receive,
please follow this link in order to unsubscribe from this list: http://lists.ercot.com.