NOTICE DATE:  September 29, 2011

NOTICE TYPE:  W-A062111-03 Operations

SHORT DESCRIPTION:  Modified Notification of Suspension of Operations for CPS Energy to remove Braunig Unit 3

INTENDED AUDIENCE:  ERCOT Market Participants

DAY AFFECTED:  September 30, 2011

LONG DESCRIPTION:  ERCOT received a Notification of Suspension of Operations (NSO) from CPS Energy on June 21, 2011, for the following Generation Resources:

On July 15, 2011, ERCOT issued its Initial and Final Determination that these Generation Resources were not required to support ERCOT System reliability and that they would suspend operations starting September 30, 2011, in accordance with the schedule in the NSO.

On September 27, 2011, ERCOT received a modified NSO from CPS Energy in which BRAUNIG_VHB3 was removed from the NSO as CPS Energy will now keep this Resource operational.

ADDITIONAL INFORMATION:  The Notification of Suspension of Operations and the analysis performed to arrive at ERCOT’s determination are posted on the ERCOT Market Information System (MIS) Secure Area on the Grid/Generation page under Reliability Must Run at https://mis.ercot.com/pps/tibco/mis/Pages/Grid+Information/Generation. An ERCOT digital certificate is required to access the MIS.

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask].

If you are receiving email from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.

 

 

 

 

dh

 



To unsubscribe from the NOTICE_CRR list, click the following link:
http://lists.ercot.com/SCRIPTS/WA-ERCOT.EXE?SUBED1=NOTICE_CRR&A=1