NOTICE DATE:  September 26, 2011

NOTICE TYPE:  W-A092311-02 Operations

SHORT DESCRIPTION:  The ERCOT MOTE will be open for DST testing

INTENDED AUDIENCE:  QSE operations personnel

DAYS AFFECTED:  October 11-14, 25-28 and November 1-4, 2011

LONG DESCRIPTION: 

SUBMISSIONS

For information regarding submissions, including Daylight Saving Time requirements, please refer to the latest version of the EIP External Interface Specifications document for use of the External Web Services (EWS) found in the Wholesale section of the http://www.ercot.com/services/mdt/xsds/ webpage. The most recent External Web Services XSD may also be found in the same location.

During testing, the URL for XML submissions will be: https://testingapi.ercot.com/2007-08/Nodal/eEDS/EWS/. The URL for UI submissions will be: https://testing.ercot.com/mmsui/mmsui/displayTradesLanding.action.

Submissions will be using the asterisk (*) on the repeating hour for DST. The following is an example of how the hourly intervals for November 6, 2011 are labeled:

0100

0200

0200*

0300

0400…

ADDITIONAL INFORMATION:  The Qualified Scheduling Entity Managers Working Group (QMWG) meeting on October 10, 2011, will include a DST Testing Q&A agenda item with ERCOT EMS/MMS Subject Matter Experts (SMEs) available to provide responses.

ERCOT will be sending information regarding extracts and reports in an update notice later this week.

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask].

If you are receiving email from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.

 

 

 

 

 

ad

 

 

From: ERCOT Client Services
Sent: Friday, September 23, 2011 4:34 PM
To: [log in to unmask]
Cc: 1 ERCOT Client Service Reps; [log in to unmask]; [log in to unmask]
Subject: W-A092311-01 ERCOT MOTE Daylight Saving Time Testing

 

NOTICE DATE:  September 23, 2011

NOTICE TYPE:  W-A092311-01 Operations

SHORT DESCRIPTION:  The ERCOT MOTE will be open for DST testing

INTENDED AUDIENCE:  QSE operations personnel

DAYS AFFECTED:  See table below

LONG DESCRIPTION:  The ERCOT Market Operations Test Environment (MOTE) will be available for Market Participant Daylight Saving Time (DST) testing for the three periods listed in the table below. Each testing period will be from Tuesday through Friday and will follow the simulated times shown in the table. The MOTE will be unavailable on Monday of each testing week to allow ERCOT to prepare for the tests.

MOTE DST Testing

 

 

Real-time

Simulated time

 

10/11/2011   08:00

11/03/2011   08:00

Start testing QSE submissions for Long Day 11/06/2011

10/12/2011   10:00

11/04/2011   10:00

 

10/13/2011   10:00

11/05/2011   10:00

DAM close for Operating Day 11/06/2011

10/14/2011   02:00

11/06/2011   02:00

DST Transition Time

10/14/2011   03:00

11/06/2011   02:00*

 

10/14/2011   12:00

11/07/2011   11:00

Close of Test

 

 

 

Real-time

Simulated time

 

10/25/2011   08:00

11/03/2011   08:00

Start testing QSE submissions for Long Day 11/06/2011

10/26/2011   10:00

11/04/2011   10:00

 

10/27/2011   10:00

11/05/2011   10:00

DAM close for Operating Day 11/06/2011

10/28/2011   02:00

11/06/2011   02:00

DST Transition Time

10/28/2011   03:00

11/06/2011   02:00*

 

10/28/2011   12:00

11/07/2011   11:00

Close of Test

 

 

 

Real-time

Simulated time

 

11/01/2011   08:00

11/03/2011   08:00

Start testing QSE submissions for Long Day 11/06/2011

11/02/2011   10:00

11/04/2011   10:00

 

11/03/2011   10:00

11/05/2011   10:00

DAM close for Operating Day 11/06/2011

11/04/2011   02:00

11/06/2011   02:00

DST Transition Time

11/04/2011   03:00

11/06/2011   02:00*

 

11/04/2011   12:00

11/07/2011   11:00

Close of Test

 

ADDITIONAL INFORMATION:  ERCOT will be sending information regarding submissions and extracts and reports in update notices next week.

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask].

If you are receiving email from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.

 

 

 

 

 

dh

 



To unsubscribe from the NOTICE_TRAINING list, click the following link:
http://lists.ercot.com/SCRIPTS/WA-ERCOT.EXE?SUBED1=NOTICE_TRAINING&A=1