NOTICE DATE:  March 7, 2012

NOTICE TYPE:  W-A030712-01 Operations

SHORT DESCRIPTION:  Review of annual Congestion Management Plans

INTENDED AUDIENCE:  Transmission Operators

DAY AFFECTED:  April 15, 2012
LONG DESCRIPTION:  ERCOT has posted the study case that will be used to review Congestion Management Plans, which includes Remedial Action Plans (RAPs), Mitigation Plans (MPs) and Pre-Contingency Action Plans (PCAPs), on the Planning and Operations Information site at http://planning.ercot.com/data/opsreview/.
Transmission Operators with existing RAPs, MPs and PCAPs are urged to review these and comment on the need to keep the plans in place or make updates to them.
Existing Congestion Management Plans can be found on the ERCOT Market Information System (MIS) under "Special Protection Systems and Remedial Action Plans" at https://mis.ercot.com/pps/tibco/mis/Pages/Grid+Information/Long+Term+Planning. A digital certificate is required to access the MIS.
ACTION REQUIRED:  Provide comments on existing RAPs, MPs and PCAPs by April 15, 2012, to [log in to unmask]<mailto:[log in to unmask]>.

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask]<mailto:[log in to unmask]>.
If you are receiving email from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com<http://lists.ercot.com/>.




dh