ERCOT has shut down all NAESB inbound and outbound transaction processing, MarkeTrak, and Retail MIS.  

 

DH/JR

 

From: ERCOT Client Services
Sent: Thursday, June 07, 2012 1:39 PM
To: [log in to unmask]; [log in to unmask]; [log in to unmask]; [log in to unmask]; [log in to unmask]
Cc: [log in to unmask]; [log in to unmask]; [log in to unmask]; 1 ERCOT Client Service Reps; RMS and others; 1 Standard Electronic Transactions
Subject: M-C050112-07 REMINDER - Release – Retail - Texas SET V4.0 Implementation - 12:00 Friday, June 8, 2012 through 00:00 Monday, June 11, 2012

 

NOTICE DATE:  June 7, 2012

NOTICE TYPE:  M-C050112-07 REMINDER: Release – Retail: Texas SET V4.0 Implementation

SHORT DESCRIPTION:  Texas SET V4.0 implementation dates - market shutdown timeline and mandatory market calls

INTENDED AUDIENCE:  All Market Participants

DAYS AFFECTED: 12:00 Friday, June 8, 2012 through 00:00 Monday, June 11, 2012

LONG DESCRIPTION: The details for the market shutdown for Texas SET Version 4.0 migration may be referenced in the Texas SET Version 4.0 Production Implementation Plan posted on the Market Coordination Team (MCT) Webpage of the ERCOT website (http://www.ercot.com/committees/board/tac/rms/mct/index.html). 

The spreadsheet is also attached to this notice. Included in the implementation plan, as well as below, is the market conference call timeline. 

 

Friday, June 8, 2012

Time

Task

Entity

8:00 AM

CRs suspend sending 814 transactions to ERCOT (both EDI and through retail portion of MIS)

All CRs

 

CRs begin using safety net process as needed for submitting MVIs with a requested date of June 8 - June 12

All CRs

 

CRs begin using emergency reconnect for non-payment spreadsheet process as needed for submitting reconnects for non-payment

All CRs

 

CRs suspend 814_PC transactions

All CRs

 

CRs suspend 650_01 transactions

All CRs

 

TDSPs suspend 650_04 transactions

All TDSPs

 

TDSPs suspend 814_20 transactions

All TDSPs

9:00 AM

TDSPs suspend 867s and 814 responses

All TDSPs

 

CRs suspend 824 transactions

All CRs

 

TDSPs suspend 814_PD transactions

All TDSPs

 

TDSPs suspend 650_02 transactions

All TDSPs

 

CRs suspend 650_05 transactions

All CRs

 

TDSPs to log MarkeTrak Issue with ERCOT for AMS initial load file (excludes Sharyland and Nueces)

All TDSPs

10:00 AM

Third Market Conference Call - ERCOT confirmation of transaction suspension.  Update on transaction processing.

All MPs

12:00 PM

TDSPs suspend 810_02 (820_03MC) transactions

All TDSPs

 

CRs suspend 820_02 (810_03MC) transactions

All CRs

 

997s suspended for all transactions

All MPs

 

ERCOT shuts down inbound and outbound processing and MarkeTrak

ERCOT

 

ERCOT sends out system shutdown email to market

ERCOT

 

 

ACTION REQUIRED: All LSEs and TDSPs must participate in the mandatory market calls.  Please note the information below for specific dates and times for the mandatory market calls.  The dial in number and pass code for all of the calls are the same. ERCOT requests that all participants from the same company dial in from a centralized location to make sure that lines are available for all market participants. Call dates and times are as follows:

Tuesday, June 5, 14:00 CPT

Thursday, June 7, 16:00 CPT
Friday, June 8, 10:00 CPT
Saturday, June 9, 12:00 CPT
Saturday, June 9, 18:00 CPT
Sunday, June 10, 10:00 CPT

Meeting information

 

To join the meetings, go to: https://ercot.webex.com/ercot/j.php?ED=191999682&UID=482806862&PW=NYWIxYWMzMjUx&RT=MiM3

-------------------------------------------------------

Topic: TX 4.0 Market Calls
Meeting Number: 659 806 314
Meeting Password: Set4mc
-------------------------------------------------------

Audio conference information
Call-in toll-free number: 1-877-668-4493
Access code: 659 806 314

Muting Instructions: To ensure no interference with your call, please inform all parties of the following:
A. If you are using a speaker phone, please mute the speaker.
B. If you need to mute/un-mute your phone, press *6
C. If at any time you need operator assistance, press *0

 

ADDITIONAL INFORMATION:  For references to Texas SET V4.0 functionality for this release, please use the following link to the Market Coordination Team (MCT) webpage on the ERCOT website: http://www.ercot.com/committees/board/tac/rms/mct/index.html.

During this outage the following functions will be affected:

 

·         The following reports and extracts will be impacted due to the outage timeframe:

o   997 Report EMIL ID: NP19-4

o   Potential Load Loss Report EMIL ID:COMS-428

o   Siebel Service Order Extract EMIL ID: COMS-163

o   Market Participant Dispute Extract EMIL ID: NP9-515

o   ERCOT Summary Dispute Report EMIL ID: NP9-592

 

The Data Definition Language (DDLs) for the TDSP ESIID Extract and the Siebel Service Order Extract have been posted at: http://www.ercot.com/services/mdt/ddls/index

The Document Type Definitions (DTDs) for the TDSP ESIID Extract and the Siebel Service Order Extract have been posted at: http://www.ercot.com/services/mdt/xsds

CONTACT:  Listed below for your reference are the ERCOT business and technical contacts for Texas SET V4.0.  Should you have any questions relating to your company’s Version 4.0 implementation plans, we suggest you contact your company’s Version 4.0 Market Coordination Team representative.

ERCOT Market Liaison

Gene Cervenka

[log in to unmask]

512.248.3903 (Office)

512.695.5199 (Cell)

 

ERCOT Project Manager

Leo Castillo

[log in to unmask]

512.248.4677 (Office)

214.797.1541 (Cell)

 

ERCOT Sr. Data Analyst

Kathryn Thurman

[log in to unmask]

512.248.6747 (Office)

512.636.6629 (Cell)

 

Should you have any other questions, please contact your Retail Account Manager.  You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via e-mail at [log in to unmask].

 

If you are receiving e-mail from an ERCOT distribution list that  you no longer wish to receive, please follow this link in order to unsubscribe from this list:  http://lists.ercot.com.

 

DH/JR

316772

 

 

From: ERCOT Client Services
Sent: Monday, June 04, 2012 2:19 PM
To: [log in to unmask]; [log in to unmask]; [log in to unmask]; [log in to unmask]; [log in to unmask]
Cc: [log in to unmask]; [log in to unmask]; [log in to unmask]; 1 ERCOT Client Service Reps; RMS and others; 1 Standard Electronic Transactions
Subject: M-C050112-06 UPDATE - Release – Retail - Texas SET V4.0 Implementation

 

NOTICE DATE:  June 4, 2012

NOTICE TYPE:  M-C050112-06 UPDATE: Release – Retail: Texas SET V4.0 Implementation

SHORT DESCRIPTION:  Texas SET V4.0 implementation dates - market shutdown timeline and mandatory market calls

INTENDED AUDIENCE:  All Market Participants

DAYS AFFECTED: June 8, 2012 – June 11, 2012

LONG DESCRIPTION:  The critical system failure at CenterPoint Energy that resulted in the delay of ERCOT’s TX SET 4.0 retail release has now been resolved. Centerpoint Energy reported today that recovery efforts continue but that it is able to support the market proceeding with the implementation of TXSET Version 4.0 this week following the schedule in the table below. 

 

The details for the market shutdown for Texas SET Version 4.0 migration may be referenced in the Texas SET Version 4.0 Production Implementation Plan posted on the Market Coordination Team (MCT) Webpage of the ERCOT website (http://www.ercot.com/committees/board/tac/rms/mct/index.html). 

The spreadsheet is also attached to this notice. Included in the implementation plan, as well as below, is the market conference call timeline. 

 

 

Tuesday, June 5, 2012

Time

Task

Entity

2:00 PM

1st Market Conference Call - Confirm all MPs are ready to proceed with TX SET V4.0 implementation

All MPs

 

Wednesday, June 6, 2012

Time

Task

Entity

12:00 PM

CRs suspend sending 650_01 DNP Transactions - Pending DNPs will continue to be worked according to the DNP procedures

All CRs

5:00 PM

TDSPs will flush systems to cancel all pending 650 DNPs and send complete unexecutables to CRs

All TDSPs

 

Thursday, June 7, 2012

Time

Task

Entity

4:00 PM

2nd Market Conference Call - Confirm DNPs are suspended; Roll call for TDSPs only

All MPs

 

Friday, June 8, 2012

Time

Task

Entity

8:00 AM

CRs suspend sending 814 transactions to ERCOT (both EDI and through Retail portion of MIS)

All CRs

 

CRs begin using Safety Net process as needed for submitting MVIs with a requested date of June 8 - June 12

All CRs

 

CRs begin using Emergency Reconnect for non-payment spreadsheet process as needed for submitting Reconnects for Non-Payment

All CRs

 

CRs suspend 814_PC transactions

All CRs

 

CRs suspend 650_01 transactions

All CRs

 

TDSPs suspend 650_04 transactions

All TDSPs

 

TDSPs suspend 814_20 transactions

All TDSPs

9:00 AM

TDSPs suspend 867s and 814 responses

All TDSPs

 

CRs suspend 824 transactions

All CRs

 

TDSPs suspend 814_PD transactions

All TDSPs

 

TDSPs suspend 650_02 transactions

All TDSPs

 

CRs suspend 650_05 transactions

All CRs

 

TDSPs to log MarkeTrak Issue with ERCOT for AMS Initial load file (excludes Sharyland and Nueces)

All TDSPs

10:00 AM

3rd Market Conference Call - ERCOT confirmation of transaction suspension.  Update on transaction processing.

All MPs

12:00 PM

TDSPs suspend 810_02 (820_03MC) transactions

All TDSPs

 

CRs suspend 820_02 (810_03MC) transactions

All CRs

 

997s suspended for all transactions

All MPs

 

ERCOT shuts down inbound and outbound processing and MarkeTrak

ERCOT

 

ERCOT sends out System Shutdown email to market

ERCOT

 

Saturday, June 9, 2012

Time

Task

Entity

12:00 PM

4th Market Conference Call - MP Migration Status

All MPs

6:00 PM

5th Market Conference Call - MP Migration Status

All MPs

 

Sunday, June 10, 2012

Time

Task

Entity

10:00 AM

6th Market Conference Call - MP Migration Status; Confirm Market Readiness

All MPs

 

 

ACTION REQUIRED: All LSEs and TDSPs must participate in the mandatory market calls.  Please note the information below for specific dates and times for the mandatory market calls.  The dial in number and pass code for all of the calls are the same. ERCOT requests that all participants from the same company dial in from a centralized location to make sure that lines are available for all market participants. Call dates and times are as follows:

Tuesday, June 5, 14:00 CPT

Thursday, June 7, 16:00 CPT
Friday, June 8, 10:00 CPT
Saturday, June 9, 12:00 CPT
Saturday, June 9, 18:00 CPT
Sunday, June 10, 10:00 CPT

Meeting information

 

To join the meetings, go to: https://ercot.webex.com/ercot/j.php?ED=191999682&UID=482806862&PW=NYWIxYWMzMjUx&RT=MiM3

-------------------------------------------------------

Topic: TX 4.0 Market Calls
Meeting Number: 659 806 314
Meeting Password: Set4mc
-------------------------------------------------------

Audio conference information
Call-in toll-free number: 1-877-668-4493
Access code: 659 806 314

Muting Instructions: To ensure no interference with your call, please inform all parties of the following:
A. If you are using a speaker phone, please mute the speaker.
B. If you need to mute/un-mute your phone, press *6
C. If at any time you need operator assistance, press *0

 

ADDITIONAL INFORMATION:  For references to Texas SET V4.0 functionality for this release, please use the following link to the Market Coordination Team (MCT) webpage on the ERCOT website: http://www.ercot.com/committees/board/tac/rms/mct/index.html.

During this outage the following functions will be affected:

 

·         The following reports and extracts will be impacted due to the outage timeframe:

o   997 Report EMIL ID: NP19-4

o   Potential Load Loss Report EMIL ID:COMS-428

o   Siebel Service Order Extract EMIL ID: COMS-163

o   Market Participant Dispute Extract EMIL ID: NP9-515

o   ERCOT Summary Dispute Report EMIL ID: NP9-592

 

The Data Definition Language (DDLs) for the TDSP ESIID Extract and the Siebel Service Order Extract have been posted at: http://www.ercot.com/services/mdt/ddls/index

The Document Type Definitions (DTDs) for the TDSP ESIID Extract and the Siebel Service Order Extract have been posted at: http://www.ercot.com/services/mdt/xsds

CONTACT:  Listed below for your reference are the ERCOT business and technical contacts for Texas SET V4.0.  Should you have any questions relating to your company’s Version 4.0 implementation plans, we suggest you contact your company’s Version 4.0 Market Coordination Team representative.

ERCOT Market Liaison

Gene Cervenka

[log in to unmask]

512.248.3903 (Office)

512.695.5199 (Cell)

 

ERCOT Project Manager

Leo Castillo

[log in to unmask]

512.248.4677 (Office)

214.797.1541 (Cell)

 

ERCOT Sr. Data Analyst

Kathryn Thurman

[log in to unmask]

512.248.6747 (Office)

512.636.6629 (Cell)

 

Should you have any other questions, please contact your Retail Account Manager.  You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via e-mail at [log in to unmask].

 

If you are receiving e-mail from an ERCOT distribution list that  you no longer wish to receive, please follow this link in order to unsubscribe from this list:  http://lists.ercot.com.

 

JR/DH

316772

 

From: ERCOT Client Services
Sent: Friday, June 01, 2012 1:59 PM
To: [log in to unmask]; [log in to unmask]; [log in to unmask]; [log in to unmask]; [log in to unmask]
Cc: [log in to unmask]; [log in to unmask]; [log in to unmask]; 1 ERCOT Client Service Reps; RMS and others; 1 Standard Electronic Transactions
Subject: M-C050112-05 UPDATE - Release – Retail: Texas SET V4.0 Implementation - URGENT

 

NOTICE DATE:  June 1, 2012

NOTICE TYPE:  M-C050112-05 UPDATE: Release – Retail: Texas SET V4.0 Implementation

SHORT DESCRIPTION:  TX SET Version 4.0 retail release is delayed

INTENDED AUDIENCE:  All Market Participants

DAY AFFECTED: June 1, 2012 – June 4, 2012

LONG DESCRIPTION:  ERCOT’s retail release of TX SET 4.0 scheduled for this weekend has been delayed until next weekend, June 8 – 11, 2012. ERCOT is exercising the current contingency option in the TX SET 4.0 Implementation Plan due to a critical system failure at CenterPoint Energy. The tentative schedule for next week is in the table below. CenterPoint will be providing status updates on their recovery efforts through daily market notices and on the market conference call scheduled for 10:00 CPT on Monday, June 4, 2012.

 

A determination on whether to move forward with the schedule below will be made during the market call on Monday, June 4, 2012 at 10:00 CPT.

 

 

Tuesday, June 5, 2012

Time

Task

Entity

2:00 PM

1st Market Conference Call - Confirm all MPs are ready to proceed with TX SET V4.0 implementation

All MPs

 

Wednesday, June 6, 2012

Time

Task

Entity

12:00 PM

CRs suspend sending 650_01 DNP Transactions - Pending DNPs will continue to be worked according to the DNP procedures

All CRs

5:00 PM

TDSPs will flush systems to cancel all pending 650 DNPs and send complete unexecutables to CRs

All TDSPs

 

Thursday, June 7, 2012

Time

Task

Entity

4:00 PM

2nd Market Conference Call - Confirm DNPs are suspended; Roll call for TDSPs only

All MPs

 

Friday, June 8, 2012

Time

Task

Entity

8:00 AM

CRs suspend sending 814 transactions to ERCOT (both EDI and through Retail portion of MIS)

All CRs

 

CRs begin using Safety Net process as needed for submitting MVIs with a requested date of June 8 - June 12

All CRs

 

CRs begin using Emergency Reconnect for non-payment spreadsheet process as needed for submitting Reconnects for Non-Payment

All CRs

 

CRs suspend 814_PC transactions

All CRs

 

CRs suspend 650_01 transactions

All CRs

 

TDSPs suspend 650_04 transactions

All TDSPs

 

TDSPs suspend 814_20 transactions

All TDSPs

9:00 AM

TDSPs suspend 867s and 814 responses

All TDSPs

 

CRs suspend 824 transactions

All CRs

 

TDSPs suspend 814_PD transactions

All TDSPs

 

TDSPs suspend 650_02 transactions

All TDSPs

 

CRs suspend 650_05 transactions

All CRs

 

TDSPs to log MarkeTrak Issue with ERCOT for AMS Initial load file (excludes Sharyland and Nueces)

All TDSPs

10:00 AM

3rd Market Conference Call - ERCOT confirmation of transaction suspension.  Update on transaction processing.

All MPs

12:00 PM

TDSPs suspend 810_02 (820_03MC) transactions

All TDSPs

 

CRs suspend 820_02 (810_03MC) transactions

All CRs

 

997s suspended for all transactions

All MPs

 

ERCOT shuts down inbound and outbound processing and MarkeTrak

ERCOT

 

ERCOT sends out System Shutdown email to market

ERCOT

 

Saturday, June 9, 2012

Time

Task

Entity

12:00 PM

4th Market Conference Call - MP Migration Status

All MPs

6:00 PM

5th Market Conference Call - MP Migration Status

All MPs

 

Sunday, June 10, 2012

Time

Task

Entity

10:00 AM

6th Market Conference Call - MP Migration Status; Confirm Market Readiness

All MPs

 

 

ACTION REQUIRED: All LSEs and TDSPs must attend the mandatory market call on

Monday, June 4, at 10:00 CPT.

Meeting information

To join the meetings, go to: https://ercot.webex.com/ercot/j.php?ED=191999682&UID=482806862&PW=NYWIxYWMzMjUx&RT=MiM3

-------------------------------------------------------

Topic: TX 4.0 Market Calls
Meeting Number: 659 806 314
Meeting Password: Set4mc
-------------------------------------------------------

Audio conference information
Call-in toll-free number: 1-877-668-4493
Access code:659 806 314

Muting Instructions: To ensure no interference with your call, please inform all parties of the following:
A. If you are using a speaker phone, please mute the speaker.
B. If you need to mute/un-mute your phone, press *6
C. If at any time you need operator assistance, press *0

ADDITIONAL INFORMATION:  An updated full implementation plan will be communicated following confirmation of the contingency date.  The following information is related to the Safety Net process for Move-Ins. The dates are contingent on final migration schedule.

 

  Beginning Friday, June 8 at 08:00 CPT, the CRs will utilize the approved Safety Net process during implementation with a default BGN02 value to request Move-Ins with requested dates during migration period. If the REP cannot include the actual BGN02, the BGN02 must use the following format (cannot exceed 30 characters):

÷  First 3 spaces=  V40

÷  Next 3 spaces= Abbreviated CR name

÷  Then followed by a unique number for each transaction

 

  CRs will be required to follow up with the corrected BGN02 on a Safety Net correction to the TDSP once their actual BGN02 is available.

  TDSPs will no longer accept default BGN values on Monday, June 11 at 08:00 CPT or as soon as Texas SET Version 4.0 transactions begin to flow.

CONTACT:  Listed below for your reference are the ERCOT business and technical contacts for Texas SET V4.0.  Should you have any questions relating to your company’s Version 4.0 implementation plans, we suggest you contact your company’s Version 4.0 Market Coordination Team representative.

ERCOT Market Liaison

Gene Cervenka

[log in to unmask]

512.248.3903 (Office)

512.695.5199 (Cell)

 

ERCOT Project Manager

Leo Castillo

[log in to unmask]

512.248.4677 (Office)

214.797.1541 (Cell)

 

ERCOT Sr. Data Analyst

Kathryn Thurman

[log in to unmask]

512.248.6747 (Office)

512.636.6629 (Cell)

 

Should you have any other questions, please contact your Retail Account Manager.  You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via e-mail at [log in to unmask].

 

If you are receiving e-mail from an ERCOT distribution list that  you no longer wish to receive, please follow this link in order to unsubscribe from this list:  http://lists.ercot.com.

 

JR/

316772

 

 

 

From: ERCOT Client Services
Sent: Thursday, May 31, 2012 4:49 PM
To: [log in to unmask]; [log in to unmask]; [log in to unmask]; [log in to unmask]; [log in to unmask]
Cc: [log in to unmask]; [log in to unmask]; [log in to unmask]; 1 ERCOT Client Service Reps; RMS and others; 1 Standard Electronic Transactions
Subject: M-C050112-04 UPDATE - POSTPONED - Release – Retail: Texas SET V4.0 Implementation - URGENT
Importance: High

 

The ERCOT planned retail release scheduled for this weekend has been delayed until next weekend. Any previously planned activities for Friday, June 1 excluding the 10:00 conference call will no longer take place.

 

The four hour switch hold workaround will not be utilized on June 1 as previously planned.

 

All market participants are required to attend the 10:00 conference call scheduled for Friday, June 1 to discuss the revised schedule and address all questions.

 

The schedule with the new proposed dates is in the table below and will be discussed during the mandatory 10:00 call. Once the schedule is finalized, a market notice will be sent with the update.

 

 

Tuesday, June 5, 2012

Time

Task

Entity

2:00 PM

1st Market Conference Call - Confirm all MPs are ready to proceed with TX SET V4.0 implementation

All MPs

 

Wednesday, June 6, 2012

Time

Task

Entity

12:00 PM

CRs suspend sending 650_01 DNP Transactions - Pending DNPs will continue to be worked according to the DNP procedures

All CRs

5:00 PM

TDSPs will flush systems to cancel all pending 650 DNPs and send complete unexecutables to CRs

All TDSPs

 

Thursday, June 7, 2012

Time

Task

Entity

4:00 PM

2nd Market Conference Call - Confirm DNPs are suspended; Roll call for TDSPs only

All MPs

 

Friday, June 8, 2012

Time

Task

Entity

8:00 AM

CRs suspend sending 814 transactions to ERCOT (both EDI and through Retail portion of MIS)

All CRs

 

CRs begin using Safety Net process for as needed for submitting MVIs with a requested date of June 1 - June 5

All CRs

 

CRs begin using Emergency Reconnect for non-payment spreadsheet process as needed for submitting Reconnects for Non-Payment

All CRs

 

CRs suspend 814_PC transactions

All CRs

 

CRs suspend 650_01 transactions

All CRs

 

TDSPs suspend 650_04 transactions

All TDSPs

 

TDSPs suspend 814_20 transactions

All TDSPs

9:00 AM

TDSPs suspend 867s and 814 responses

All TDSPs

 

CRs suspend 824 transactions

All CRs

 

TDSPs suspend 814_PD transactions

All TDSPs

 

TDSPs suspend 650_02 transactions

All TDSPs

 

CRs suspend 650_05 transactions

All CRs

 

TDSPs to log MarkeTrak Issue with ERCOT for AMS Initial load file (excludes Sharyland and Nueces)

All TDSPs

10:00 AM

3rd Market Conference Call - ERCOT confirmation of transaction suspension.  Update on transaction processing.

All MPs

12:00 PM

TDSPs suspend 810_02 (820_03MC) transactions

All TDSPs

 

CRs suspend 820_02 (810_03MC) transactions

All CRs

 

997s suspended for all transactions

All MPs

 

ERCOT shuts down inbound and outbound processing and MarkeTrak

ERCOT

 

ERCOT sends out System Shutdown email to market

ERCOT

 

Saturday, June 9, 2012

Time

Task

Entity

12:00 PM

4th Market Conference Call - MP Migration Status

All MPs

6:00 PM

5th Market Conference Call - MP Migration Status

All MPs

 

Sunday, June 10, 2012

Time

Task

Entity

10:00 AM

6th Market Conference Call - MP Migration Status; Confirm Market Readiness

All MPs

 

 

 

JR/DH

 

 

From: ERCOT Client Services
Sent: Thursday, May 31, 2012 2:47 PM
To: [log in to unmask]; [log in to unmask]; [log in to unmask]; [log in to unmask]; [log in to unmask]
Cc: [log in to unmask]; [log in to unmask]; [log in to unmask]; 1 ERCOT Client Service Reps; RMS and others; 1 Standard Electronic Transactions
Subject: M-C050112-03 REMINDER - Release – Retail: Texas SET V4.0 Implementation - 12:00 Friday, June 1, 2012 through 00:00 Monday, June 4, 2012

 

NOTICE DATE:  May 31, 2012

NOTICE TYPE:  M-C050112-03 REMINDER: Release – Retail: Texas SET V4.0 Implementation

SHORT DESCRIPTION:  Texas SET V4.0 market shutdown timeline and mandatory market calls

INTENDED AUDIENCE:  All Market Participants

DAYS AFFECTED: 12:00 Friday, June 1, 2012 through 00:00 Monday, June 4, 2012

LONG DESCRIPTION:  The details for the market shutdown for Texas SET Version 4.0 migration may be referenced in the Texas SET Version 4.0 Production Implementation Plan posted on the Market Coordination Team (MCT) Webpage of the ERCOT website (http://www.ercot.com/committees/board/tac/rms/mct/index.html). 

The spreadsheet is also attached to this notice. Included in the implementation plan, as well as below, is the market conference call timeline. 

 

Friday, June 1, 2012

Time

Task

Entity

8:00 AM

CRs suspend sending 814 transactions to ERCOT (both EDI and through retail portion of MIS)

All CRs

 

CRs begin using safety net process for as needed for submitting MVIs with a requested date of June 1 - June 5

All CRs

 

CRs begin using emergency reconnect for non-payment spreadsheet process as needed for submitting reconnects for non-payment

All CRs

 

CRs suspend 814_PC transactions

All CRs

 

CRs suspend 650_01 transactions

All CRs

 

TDSPs suspend 650_04 transactions

All TDSPs

 

TDSPs suspend 814_20 transactions

All TDSPs

9:00 AM

TDSPs suspend 867s and 814 responses

All TDSPs

 

CRs suspend 824 transactions

All CRs

 

TDSPs suspend 814_PD transactions

All TDSPs

 

TDSPs suspend 650_02 transactions

All TDSPs

 

CRs suspend 650_05 transactions

All CRs

 

TDSPs to log MarkeTrak Issue with ERCOT for AMS initial load file (excludes Sharyland and Nueces)

All TDSPs

10:00 AM

Third Market Conference Call - ERCOT confirmation of transaction suspension.  Update on transaction processing.

All MPs

12:00 PM

TDSPs suspend 810_02 (820_03MC) transactions

All TDSPs

 

CRs suspend 820_02 (810_03MC) transactions

All CRs

 

997s suspended for all transactions

All MPs

 

ERCOT shuts down inbound and outbound processing and MarkeTrak

ERCOT

 

ERCOT sends out system shutdown email to market

ERCOT

ACTION REQUIRED: All LSEs and TDSPs must participate in the mandatory market calls.  Please note the information below for specific dates and times for the mandatory market calls.  The dial in number and pass code for all of the calls are the same. ERCOT requests that all participants from the same company dial in from a centralized location to make sure that lines are available for all market participants. Call dates and times are as follows:

Tuesday, May 29, 14:00 CPT

Thursday, May 31, 16:00 CPT
Friday, June 1, 10:00 CPT
Saturday, June 2, 12:00 CPT
Saturday, June 2, 18:00 CPT
Sunday, June 3, 10:00 CPT

Meeting information

To join the meetings, go to: https://ercot.webex.com/ercot/j.php?ED=191999682&UID=482806862&PW=NYWIxYWMzMjUx&RT=MiM3

-------------------------------------------------------

Topic: TX 4.0 Market Calls
Meeting Number: 659 806 314
Meeting Password: Set4mc
-------------------------------------------------------

Audio conference information
Call-in toll-free number: 1-877-668-4493
Access code: 659 806 314

Muting Instructions: To ensure no interference with your call, please inform all parties of the following:
A. If you are using a speaker phone, please mute the speaker.
B. If you need to mute/un-mute your phone, press *6
C. If at any time you need operator assistance, press *0

 

ADDITIONAL INFORMATION:  For references to Texas SET V4.0 functionality for this release, please use the following link to the Market Coordination Team (MCT) webpage on the ERCOT website: http://www.ercot.com/committees/board/tac/rms/mct/index.html.

During this outage the following functions will be affected:

·         The following reports and extracts will be impacted due to the outage timeframe:

o   997 Report EMIL ID: NP19-4

o   Potential Load Loss Report EMIL ID:COMS-428

o   Siebel Service Order Extract EMIL ID: COMS-163

o   Market Participant Dispute Extract EMIL ID: NP9-515

o   ERCOT Summary Dispute Report EMIL ID: NP9-592

 

The Data Definition Language (DDLs) for the TDSP ESIID Extract and the Siebel Service Order Extract have been posted at: http://www.ercot.com/services/mdt/ddls/index

The Document Type Definitions (DTDs) for the TDSP ESIID Extract and the Siebel Service Order Extract have been posted at: http://www.ercot.com/services/mdt/xsds

CONTACT:  Listed below for your reference are the ERCOT business and technical contacts for Texas SET V4.0.  Should you have any questions relating to your company’s Version 4.0 implementation plans, we suggest you contact your company’s Version 4.0 Market Coordination Team representative. 

ERCOT Market Liaison

Gene Cervenka

[log in to unmask]

512.248.3903 (Office)

512.695.5199 (Cell)

 

ERCOT Project Manager

Leo Castillo

[log in to unmask]

512.248.4677 (Office)

214.797.1541 (Cell)

 

ERCOT Sr. Data Analyst

Kathryn Thurman

[log in to unmask]

512.248.6747 (Office)

512.636.6629 (Cell)

 

Should you have any other questions, please contact your Retail Account Manager.  You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via e-mail at [log in to unmask].

 

If you are receiving e-mail from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list:  http://lists.ercot.com.

 

JR/DH

316772

 

 

 

From: ERCOT Client Services
Sent: Monday, May 21, 2012 1:41 PM
To: [log in to unmask]; [log in to unmask]; [log in to unmask]; [log in to unmask]; [log in to unmask]
Cc: [log in to unmask]; [log in to unmask]; [log in to unmask]; 1 ERCOT Client Service Reps
Subject: M-C050112-02 UPDATE - Release – Retail: Texas SET V4.0 Implementation - 12:00 Friday, June 1, 2012 through 00:00 Monday, June 4, 2012

 

NOTICE DATE:  May 21, 2012

NOTICE TYPE:  M-C050112-02 UPDATE: Release – Retail: Texas SET V4.0 Implementation

SHORT DESCRIPTION:  Texas SET V4.0 market shutdown timeline and mandatory market calls

INTENDED AUDIENCE:  All Market Participants

DAYS AFFECTED: 12:00 Friday, June 1, 2012 through 00:00 Monday, June 4, 2012

LONG DESCRIPTION:  The details for the market shutdown for Texas SET Version 4.0 migration may be referenced in the Texas SET Version 4.0 Production Implementation Plan posted on the Market Coordination Team (MCT) Webpage of the ERCOT website (http://www.ercot.com/committees/board/tac/rms/mct/index.html). 

The spreadsheet is also attached to this notice. Included in the implementation plan, as well as below, is the market conference call timeline. 

 

Friday, June 1, 2012

Time

Task

Entity

8:00 AM

CRs suspend sending 814 transactions to ERCOT (both EDI and through retail portion of MIS)

All CRs

 

CRs begin using safety net process for as needed for submitting MVIs with a requested date of June 1 - June 5

All CRs

 

CRs begin using emergency reconnect for non-payment spreadsheet process as needed for submitting reconnects for non-payment

All CRs

 

CRs suspend 814_PC transactions

All CRs

 

CRs suspend 650_01 transactions

All CRs

 

TDSPs suspend 650_04 transactions

All TDSPs

 

TDSPs suspend 814_20 transactions

All TDSPs

9:00 AM

TDSPs suspend 867s and 814 responses

All TDSPs

 

CRs suspend 824 transactions

All CRs

 

TDSPs suspend 814_PD transactions

All TDSPs

 

TDSPs suspend 650_02 transactions

All TDSPs

 

CRs suspend 650_05 transactions

All CRs

 

TDSPs to log MarkeTrak Issue with ERCOT for AMS initial load file (excludes Sharyland and Nueces)

All TDSPs

10:00 AM

Third Market Conference Call - ERCOT confirmation of transaction suspension.  Update on transaction processing.

All MPs

12:00 PM

TDSPs suspend 810_02 (820_03MC) transactions

All TDSPs

 

CRs suspend 820_02 (810_03MC) transactions

All CRs

 

997s suspended for all transactions

All MPs

 

ERCOT shuts down inbound and outbound processing and MarkeTrak

ERCOT

 

ERCOT sends out system shutdown email to market

ERCOT

ACTION REQUIRED: All LSEs and TDSPs must participate in the mandatory market calls.  Please note the information below for specific dates and times for the mandatory market calls.  The dial in number and pass code for all of the calls are the same. ERCOT requests that all participants from the same company dial in from a centralized location to make sure that lines are available for all market participants. Call dates and times are as follows:

Tuesday, May 29, 14:00 CPT

Thursday, May 31, 16:00 CPT
Friday, June 1, 10:00 CPT
Saturday, June 2, 12:00 CPT
Saturday, June 2, 18:00 CPT
Sunday, June 3, 10:00 CPT

Meeting information

To join the meetings, go to: https://ercot.webex.com/ercot/j.php?ED=191999682&UID=482806862&PW=NYWIxYWMzMjUx&RT=MiM3

-------------------------------------------------------

Topic: TX 4.0 Market Calls
Meeting Number: 659 806 314
Meeting Password: Set4mc
-------------------------------------------------------

Audio conference information
Call-in toll-free number: 1-877-668-4493
Access code: 659 806 314

Muting Instructions: To ensure no interference with your call, please inform all parties of the following:
A. If you are using a speaker phone, please mute the speaker.
B. If you need to mute/un-mute your phone, press *6
C. If at any time you need operator assistance, press *0

 

ADDITIONAL INFORMATION:  For references to Texas SET V4.0 functionality for this release, please use the following link to the Market Coordination Team (MCT) webpage on the ERCOT website: http://www.ercot.com/committees/board/tac/rms/mct/index.html.

During this outage the following functions will be affected:

·         The following reports and extracts will be impacted due to the outage timeframe:

o   997 Report EMIL ID: NP19-4

o   Potential Load Loss Report EMIL ID:COMS-428

o   Siebel Service Order Extract EMIL ID: COMS-163

o   Market Participant Dispute Extract EMIL ID: NP9-515

o   ERCOT Summary Dispute Report EMIL ID: NP9-592

 

The Data Definition Language (DDLs) for the TDSP ESIID Extract and the Siebel Service Order Extract have been posted at: http://www.ercot.com/services/mdt/ddls/index

 

The Document Type Definitions (DTDs) for the TDSP ESIID Extract and the Siebel Service Order Extract have been posted at: http://www.ercot.com/services/mdt/xsds. These DTDs will be effective upon implementation of TX SET 4.0.

CONTACT:  Listed below for your reference are the ERCOT business and technical contacts for Texas SET V4.0.  Should you have any questions relating to your company’s Version 4.0 implementation plans, we suggest you contact your company’s Version 4.0 Market Coordination Team representative. 

ERCOT Market Liaison

Gene Cervenka

[log in to unmask]

512.248.3903 (Office)

512.695.5199 (Cell)

 

ERCOT Project Manager

Leo Castillo

[log in to unmask]

512.248.4677 (Office)

214.797.1541 (Cell)

 

ERCOT Sr. Data Analyst

Kathryn Thurman

[log in to unmask]

512.248.6747 (Office)

512.636.6629 (Cell)

 

Should you have any other questions, please contact your Retail Account Manager.  You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via e-mail at [log in to unmask].

If you are receiving e-mail from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list:  http://lists.ercot.com.

 

 

JR/DH

316772

 

 

 

From: ERCOT Client Services
Sent: Tuesday, May 01, 2012 12:54 PM
To: [log in to unmask]; [log in to unmask]; [log in to unmask]; [log in to unmask]; [log in to unmask]
Cc: [log in to unmask]; [log in to unmask]; [log in to unmask]; 1 ERCOT Client Service Reps
Subject: M-C050112-01 INITIAL: Release – Retail: Texas SET V4.0 Implementation - 12:00 Friday, June 1, 2012 through 00:00 Monday, June 4, 2012

 

NOTICE DATE:  May 1, 2012

NOTICE TYPE:  M-C050112-01 INITIAL: Release – Retail: Texas SET V4.0 Implementation

SHORT DESCRIPTION:  Texas SET V4.0 market shutdown timeline and mandatory market calls

INTENDED AUDIENCE:  All Market Participants

DAY AFFECTED: 12:00 Friday, June 1, 2012 through 00:00 Monday, June 4, 2012

LONG DESCRIPTION:  The details for the market shutdown for Texas SET Version 4.0 migration may be referenced in the Texas SET Version 4.0 Production Implementation Plan posted on the Market Coordination Team (MCT) Webpage of the ERCOT website (http://www.ercot.com/committees/board/tac/rms/mct/index.html). Included in the implementation plan, as well as below, is the market conference call timeline.

 

Friday, June 1, 2012

Time

Task

Entity

8:00 AM

CRs suspend sending 814 transactions to ERCOT (both EDI and through Retail portion of MIS)

All CRs

 

CRs begin using Safety Net process for as needed for submitting MVIs with a requested date of June 1 - June 5

All CRs

 

CRs begin using Emergency Reconnect for non-payment spreadsheet process as needed for submitting Reconnects for Non-Payment

All CRs

 

CRs suspend 814_PC transactions

All CRs

 

CRs suspend 650_01 transactions

All CRs

 

TDSPs suspend 650_04 transactions

All TDSPs

 

TDSPs suspend 814_20 transactions

All TDSPs

9:00 AM

TDSPs suspend 867s and 814 responses

All TDSPs

 

CRs suspend 824 transactions

All CRs

 

TDSPs suspend 814_PD transactions

All TDSPs

 

TDSPs suspend 650_02 transactions

All TDSPs

 

CRs suspend 650_05 transactions

All CRs

 

TDSPs to log MarkeTrak Issue with ERCOT for AMS Initial load file (excludes Sharyland and Nueces)

All TDSPs

10:00 AM

Third Market Conference Call - ERCOT confirmation of transaction suspension.  Update on transaction processing.

All MPs

12:00 PM

TDSPs suspend 810_02 (820_03MC) transactions

All TDSPs

 

CRs suspend 820_02 (810_03MC) transactions

All CRs

 

997s suspended for all transactions

All MPs

 

ERCOT shuts down inbound and outbound processing and MarkeTrak

ERCOT

 

ERCOT sends out System Shutdown email to market

ERCOT

ACTION REQUIRED: All LSEs and TDSPs must participate in the mandatory market calls.  Please note the information below for specific dates and times for the mandatory market calls.  The dial in number and pass code for all of the calls are the same. ERCOT requests that all participants from the same company dial in from a centralized location to make sure that lines are available for all market participants. Call dates and times are as follows:

Tuesday, May 29, 14:00 CPT

Thursday, May 31, 16:00 CPT
Friday, June 1, 10:00 CPT
Saturday, June 2, 12:00 CPT
Saturday, June 2, 18:00 CPT
Sunday, June 3, 10:00 CPT

Meeting information

To join the meetings, go to: https://ercot.webex.com/ercot/j.php?ED=191999682&UID=482806862&PW=NYWIxYWMzMjUx&RT=MiM3

-------------------------------------------------------

Topic: TX 4.0 Market Calls
Meeting Number: 659 806 314
Meeting Password: Set4mc
-------------------------------------------------------

Audio conference information
Call-in toll-free number: 1-877-668-4493
Access code: 659 806 314

Muting Instructions: To ensure no interference with your call, please inform all parties of the following:
A. If you are using a speaker phone, please mute the speaker.
B. If you need to mute/un-mute your phone, press *6
C. If at any time you need operator assistance, press *0

ADDITIONAL INFORMATION:  For references to Texas SET V4.0 functionality for this release, please use the following link to the Market Coordination Team (MCT) webpage on the ERCOT website: http://www.ercot.com/committees/board/tac/rms/mct/index.html.

 

During this outage the following functions will be affected:

 

·         The following reports and extracts will be impacted due to the outage timeframe:

o   997 Report EMIL ID: NP19-4

o   Potential Load Loss Report EMIL ID:COMS-428

o   Siebel Service Order Extract EMIL ID: COMS-163

o   Market Participant Dispute Extract EMIL ID: NP9-515

o   ERCOT Summary Dispute Report EMIL ID: NP9-592

 

·         The draft version of the TX SET 4.0 Data Definition Language (DDLs) for the TDSP ESIID Extract and the Siebel Service Order Extract have been posted in the Key Documents section of the MCT page.

 

o    http://www.ercot.com/committees/board/tac/rms/mct/.

 

NOTE: The final version of these DDLs will be posted to the Services Page of the Market Information System (MIS) and ERCOT.com.

CONTACT:  Listed below for your reference are the ERCOT business and technical contacts for Texas SET V4.0.  Should you have any questions relating to your company’s Version 4.0 implementation plans, we suggest you contact your company’s Version 4.0 Market Coordination Team representative. 

ERCOT Market Liaison

Gene Cervenka

[log in to unmask]

512.248.3903 (Office)

512.695.5199 (Cell)

 

ERCOT Project Manager

Leo Castillo

[log in to unmask]

512.248.4677 (Office)

214.797.1541 (Cell)

 

ERCOT Sr. Data Analyst

Kathryn Thurman

[log in to unmask]

512.248.6747 (Office)

512.636.6629 (Cell)

 

Should you have any other questions, please contact your Retail Account Manager.  You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via e-mail at [log in to unmask].

 

If you are receiving e-mail from an ERCOT distribution list that  you no longer wish to receive, please follow this link in order to unsubscribe from this list:  http://lists.ercot.com.

 

 

JR/CD