NOTICE DATE:  January 31, 2014

NOTICE TYPE:  M-B012414-02 NPRR

SHORT DESCRIPTION:  Reminder - Implementation details for NPRR240, Proxy Energy Offer Curve

INTENDED AUDIENCE:  ERCOT Market Participants

DAY AFFECTED:  February 5, 2014

LONG DESCRIPTION:  On February 4, 2014, ERCOT will implement Nodal Protocol Revision Request (NPRR) 240, Proxy Energy Offer Curve, which was approved by the ERCOT Board on September 21, 2010.

NPRR240 states that the Entity with decision making authority over how a Resource or Split Generation Resource is offered or scheduled shall be responsible for all offers associated with each Resource, including offers represented by a proxy Energy Offer Curve.

The two reports below are being modified, with the addition of a new column, ‘Proxy Extension’, as the last column in each report representing whether Energy Offer Curves were constructed in whole or in part with proxy Energy Offer Curves. 

EMIL ID

Name

Report Type ID

NP3-968-EX   

61-day Generation Resource data in SCED (located in the 60 Day SCED Disclosure Report)

13052

NP3-987-EX 

7-day Event Trigger

10047

 

Refer to the 60-Day Reports Column Header Information posted on the User Guides page of ERCOT.com for further report information.

ADDITIONAL INFORMATION:  Pursuant to Protocol Section 21.6, Nodal Protocol Revision Implementation, ERCOT is required to provide notice as soon as practicable, but no later than ten days prior to implementation.

NPRR240 and associated documents can be found on the ERCOT website, under Market Rules, at http://www.ercot.com/mktrules/issues/nprr/226-250/240/index.

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask].

If you are receiving email from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.

 

 

dg

 

_______________________________________________

NOTICE DATE:  January 24, 2014

NOTICE TYPE:  M-B012414-01 NPRR

SHORT DESCRIPTION:  Implementation details for NPRR240, Proxy Energy Offer Curve

INTENDED AUDIENCE:  ERCOT Market Participants

DAY AFFECTED:  February 4, 2014

LONG DESCRIPTION:  On February 4, 2014, ERCOT will implement Nodal Protocol Revision Request (NPRR) 240, Proxy Energy Offer Curve, which was approved by the ERCOT Board on September 21, 2010.

NPRR240 states that the Entity with decision making authority over how a Resource or Split Generation Resource is offered or scheduled shall be responsible for all offers associated with each Resource, including offers represented by a proxy Energy Offer Curve.

The two reports below are being modified, with the addition of a new column, ‘Proxy Extension’, in each report representing whether Energy Offer Curves were constructed in whole or in part with proxy Energy Offer Curves:

EMIL ID

Name

Report Type ID

NP3-968-EX   

61-day Generation Resource data in SCED (located in the 60 Day SCED Disclosure Report)

13052

NP3-987-EX 

7-day Event Trigger

10047

 

ADDITIONAL INFORMATION:  Pursuant to Protocol Section 21.6, Nodal Protocol Revision Implementation, ERCOT is required to provide notice as soon as practicable, but no later than ten days prior to implementation.

NPRR240 and associated documents can be found on the ERCOT website, under Market Rules, at http://www.ercot.com/mktrules/issues/nprr/226-250/240/index.

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask].