NOTICE DATE: February 20, 2014
NOTICE TYPE: W-A022014-01 Operations
SHORT DESCRIPTION: Correction to Indicative Operating
Reserve Demand Curve (ORDC) postings
INTENDED AUDIENCE: ERCOT Market Participants
DATES AFFECTED: January 24, 2014 to February
20, 2014
LONG DESCRIPTION: As a result of issues identified
during analysis of the January 6, 2014 Energy Emergency Alert (EEA) event ERCOT changed the calculation of the Real Time On-Line reserve capacity (RTOLCAP) effective January 24, 2014 with the intention of correcting the error in Load Resource Responsibility
Schedules by introducing validation based on the formula Max { min{Telemetered MW, RRS schedule, max[MPC - LPC - (Regulation responsibility + Non-Spin responsibility + Down Regulation responsibility), 0]}, 0}. However, ERCOT inadvertently introduced another
change which resulted in an incorrect calculation of Real-Time On-Line Reserve Price Adder per interval (RTORPA) and Real-Time Off-Line Reserve Price Adder per interval (RTOFFPA) for the period of January 24, 2014 to February 20, 2014.
When calculating the RTORPA and RTOFFPA, ERCOT only included Resources with Telemetry MW > 0.95*LSL instead of including Resources
with Telemetry MW >= 0.95*LSL. This resulted in the exclusion of HSL of Quick Start Generation Resources (QSGR) from the calculation of RTOLCAP when their Telemetry MW was at 0 MW and LSL was 0 MW.
ERCOT has corrected this error and will post the corrected data on February 21, 2014.
CONTACT: If you have any questions, please contact
your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at
[log in to unmask].
If you are receiving email from an ERCOT distribution list that you no longer wish to receive, please follow this link in
order to unsubscribe from this list: http://lists.ercot.com.
sa