NOTICE DATE:  April 17, 2014
NOTICE TYPE:  W-A041714-01 Settlements
SHORT DESCRIPTION: Settlement for Emergency Response Service (ERS), Pilot 30-minute ERS and Pilot weather sensitive ERS for the Contract Period of June 1, 2013 through September 30, 2013 will be included on the True-up Settlement Statement for the Operating Day of October 19, 2013.
INTENDED AUDIENCE:  QSE settlement personnel
DAYS AFFECTED:  June 1, 2013 through September 30, 2013 - Contract Period
LONG DESCRIPTION:  ERCOT has settled Emergency Response Service (ERS), Pilot 30-minute ERS and Pilot weather sensitive ERS for the Contract Periods of June 1, 2013 through September 30, 2013. The affected charge types will be included on the True-up Settlement Statement for the Operating Day of October 19, 2013.  ERCOT will publish True-up Settlement Statements and Invoices for this Operating Day on April 17, 2014.

The ERS payments for the June 1, 2013 through Sept. 30, 2013, Contract Period are as follows:
Time Period

ERS Payments

Business Hours 1 (HE 0900-1300)*
ERSPAMTTOT_1

$  2,024,015.37



Business Hours 2 (HE 1400-1600)*
ERSPAMTTOT_2

$  1,068,857.13


Business Hours 3 (HE 1700-2000)*
ERSPAMTTOT_3

$  1,462,055.38


Non-Business Hours (All other hours)
ERSPAMTTOT_4

$  7,487,232.97


TOTAL for Contract Period

$  12,042,160.85


* Monday through Friday except ERCOT Holidays

The PILOT 30-minute ERS payments for the June 1, 2013 through September 30, 2013 Contract Period are as follows:
Time Period

ERS Payments

Business Hours 1 (HE 0900-1300)*
ERSPAMTTOT_1_PILOT

$  512,358.32


Business Hours 2 (HE 1400-1600)*
ERSPAMTTOT_2_PILOT

$  227,923.58


Business Hours 3 (HE 1700-2000)*
ERSPAMTTOT_3_PILOT

$  302,515.54


Non-Business Hours (All other hours)
ERSPAMTTOT_4_PILOT

$ 1,837,282.39


TOTAL for Contract Period

$ 2,880,079.83


* Monday through Friday except ERCOT Holidays

The Pilot weather sensitive ERS payments for the June 1, 2013 through Sept. 30, 2013 Contract Period are as follows:
Time Period

ERS Payments

Business Hours 2 (HE 1400-1600)*
ERSPAMTTOT_2_WS

$  28,402.92


Business Hours 3 (HE 1700-2000)*
ERSPAMTTOT_3_WS

$  37,870.56


Weekend & Holidays (HE1400-2000, Saturday, Sundays & Holidays)ERSPAMTTOT_4_WS

$  29,980.86


TOTAL for Contract Period

$  96,254.34


* Monday through Friday except ERCOT Holidays

Pursuant to Protocols Section 6.6.11.2(1), "For the resettlement of the ERS

Contract Period as described in item (2) of Section 9.14.5, the LRS will be

calculated using the True-up Load for each Operating Day in the ERS Contract

Period. True-up Load will be calculated according to the timing specified in item
(2) of Section 9.5.8, RTM True-Up Statement."
The latest Settlement Load values (RTAMLTOT) used to calculate True-up ERS and Pilot 30-minute ERS charges for the June 1, 2013 through September 30, 2013 Contract Period are as follows:
Time Period

RTAMLTOT

Business Hours 1 (HE 0900-1300)*

19,532,146.439352 MWH


Business Hours 2 (HE 1400-1600)*

14,350,233.225121 MWH


Business Hours 3 (HE 1700-2000)*

19,161,447.4358 MWH

Non-Business Hours (All other hours)

79,891,265.0703 MWH

RTAMLTOT Total for Contract Period

132,935,092.170573 MWH

* Monday through Friday except ERCOT Holidays

The latest Settlement Load values (RTAMLTOT) used to calculate True-up Pilot weather sensitive ERS charges for the June 1, 2013 through September 30, 2013 Contract Period are as follows:
Time Period

RTAMLTOT

Business Hours 2 (HE 1400-1600)*

  14,350,233.225121MWH

Business Hours 3 (HE 1700-2000)*

     19,161,447.4358 MWH


Non-Business Hours (Weekend and Holiday HE 1400-2000)


  13,964,875.630017MWH

RTAMLTOT Total for Contract Period

47,476,556.290938 MWH



* Monday through Friday except ERCOT Holidays

Pursuant to Protocols Section 9.14.5(1), "All disputes for the Settlement of the ERS Contract Period are due ten Business Days after the date that the ERS settlement was posted. ERCOT shall resolve any approved disputes upon resettlement of the ERS Contract Period, as described in Section 9.14.5(2)."

CONTACT:  If you have questions about the ERS program, please send an email to [log in to unmask]<mailto:[log in to unmask]>. If you have any other questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask]<mailto:[log in to unmask]>.
If you are receiving email from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.