NOTICE DATE:  April 23, 2014

NOTICE TYPE:  M-A042314-01 NPRR

SHORT DESCRIPTION:  Implementation details for NPRR532, NPRR555 and NPRR591

INTENDED AUDIENCE:  ERCOT Market Participants and Settlement Personnel

DAY AFFECTED:  June 1, 2014

LONG DESCRIPTION:  On June 1, 2014, ERCOT will implement Nodal Protocol Revision Request (NPRR) 532, Performance Measurement and Verification and Telemetry Requirements for Load Resources Providing Non-Spin and NPRR555, Load Resource Participation in Security-Constrained Economic Dispatch and NPRR591 As-Built Clarification and Corrections Related to NPRR568 and NPRR555.  NPRR532 enables participation in the Non-Spinning Reserve (Non-Spin) Service market for Load Resources.  NPRR555 and NPRR591 enable Demand response from Controllable Load Resources, as re-defined, to be Dispatched by Security-Constrained Economic Dispatch (SCED) based on a Real-Time Market (RTM) Energy Bid. 

New ICCP Telemetry Points:

 

NPRR555 adds the following new telemetry points to communicate Controllable Load Resources “Resource LMP”, “SCED Base Point”, “Updated Desired Base Point (UDBP)” and Congestion Flag values to the market using Inter-Control Center Communications Protocol (ICCP). Similar to the Generating Resources, Controllable Load Resources Updated Desired Base point (UDBP) is a linear interpolation from the current UDBP to the new SCED CLR base point over base point ramp duration. Controllable Load Resources Congestion Flag indicates that SCED has dispatched a CLR available for SCED dispatch below HDL similar to the one used for Generation Resource.  For any questions, please contact Client Services to get the ERCOT ICCP Support team help.

Controllable Load Resources LMP ($/MWh)

Controllable Load Resources SCED Base Point (MW)

Controllable Load Resources Updated Desired Base Point (MW)

Congestion Flag (SBBH).

New and/or updated Defined Resource Status for Load Resources:

The following Resource Statuses for Load Resources are to be used for Current Operating Plan (COP) and/or Real-Time telemetry purposes for NPRR555:

·         ONRGL – Available for Dispatch of Regulation Service by Load Frequency Control (LFC) and, for any remaining Dispatchable capacity, by SCED with an RTM Energy Bid;

·         ONCLR – Available for Dispatch of Response Reserve (RRS) Service, Non-Spinning Reserve Service or for energy as a Controllable Load Resource by SCED with an RTM Energy Bid;

·         ONRL – Available for Dispatch of under-frequency relay-type RRS Service; and

·         OUTL – Not available;

 

The following reports are being added to the Market Information System (MIS) and/or ERCOT.com:

Name

EMIL ID

Rpt. ID

Data Classification

 

 

Frequency

Monthly CLR Energy Deployment Performance Report

NP8-500-ER

13225

Certified

 

 

Monthly

Monthly Non-Spin CLR Performance Report

NP8-384-ER

13224

Secure

 

 

Monthly

48-hour Highest Priced Bids Selected or Dispatched in SCED

NP3-257-EX

13230

Public

 

Daily

Load Resource SCED Qualification Test Results

NP12-212-M

13234

Certified

 

Yearly

Load Resource Reserve Discount Factors for CLRs

NP6-575-M

13226

Public

 

As Needed

Controllable Load Resource Base Point Deviation Charge for Over-Consumption Variables

NP6-651-M

13228

Public

 

 

As Needed

Controllable Load Resource Base Point Deviation Charge for Under-Consumption Variables

NP6-652-M

13227

Public

 

 

As Needed

CLREDP Acceptable Performance Criteria

NP8-114-M

13229

Public

 

As Needed

48-hour - Aggregate Energy Demand Curves for Controllable Load Resources (located inside the 48 Hour DAM and SCED Energy Curves Reports)

NP3-908-ER

13054

Public

 

 

 

 

Daily

 

The following reports are being changed:

Name

EMIL ID

Rpt. ID

Category

New Name:  Monthly Generation Resource Energy Deployment Performance Report

Previous Name:  Monthly Resource Energy Deployment Performance Report

NP8-501-ER

11022

Certified

New Name:  Monthly Non-Spin Generation Performance Report

Previous Name:  Monthly Non-Spin Performance Report

NP8-383

11026

Secure

New Name:  Approved GREDP Reports

Previous Name:  Approved GREDP and CLREDP Performance Criteria Variables

NP8-503-M

13034

Public

Resource Control Report – SCED qualified Resources will be included, as applicable.

NP3-988-ER

10036

Public

QSE Ancillary Services Capacity Monitor – Two new columns being added to existing report:

·         Capacity from Controllable Load Resources available to decrease Base Points (energy consumption) in SCED

·         Capacity from Controllable Load Resources available to increase Base Points (energy consumption) in SCED

NP8-143-CD

11025

Certified


The System Ancillary Service Capacity Monitor dashboard will contain two new rows in the System Capacity section; additionally, the Base Points will be specified as Generation Resource Base Points in SCED

·         Capacity from Controllable Load Resources available to decrease Base Points (energy consumption) in SCED

·         Capacity from Controllable Load Resources available to increase Base Points (energy consumption) in SCED

New Market Submission Type:

A new submission type, Real-Time Market (RTM) Bids, will be added to support participation in SCED by qualified Controllable Load Resources. The type will appear in the Market Manager under the “Resource-Specific” tab, and the XML format is specified by the attached XSD documents. The MOTE environment will be available for testing submissions starting on Tuesday, April 29, 2014.

New Settlement Bill Determinants:

The following new bill determinants will be implemented for NPRR555:

Bill Determinant

Short Description

Extract

Extract Table

ATPC

Average Telemetered Power Consumption

SID/RTM MODE

MKTINPUTHEADER
MKTINPUTSCALAR

CLRASFLAG

Flag that indicates that the Controllable Load Resource has Ancillary Service responsibility

SID/RTM CODE

MKTINPUTHEADER
MKTINPUTINTERVAL

CLRDISPFLAG

Flag that indicates the computed Base Point is equal to the snapshot of its telemetered power consumption for all SCED runs during the Settlement Interval

SID/RTM CODE

MKTINPUTHEADER
MKTINPUTINTERVAL

LROFLAG

Flag that indicates that the Controllable Load Resource’s telemetered Resource Status is set to OUTL

SID/RTM CODE

MKTINPUTHEADER
MKTINPUTINTERVAL

OCONSM

Over-Consumption Volumes per QSE per Settlement Point per Controllable Load Resource

RTM/CODE

RTMOUTPUTHEADER

RTMOUTPUTINTERVAL

UCONSM

Under Consumption Volumes per QSE per Settlement Point per Controllable Load Resource

RTM/CODE

RTMOUTPUTHEADER

RTMOUTPUTINTERVAL

 

New Settlement Factor/FactorValue:

The following new Factor will be implemented for NPRR555:

Factor

Short Description

Extract

Extract Table

KP1

The coefficient applied to the Settlement Point Price for over-consumption charge

PRDE

Factor/FactorValue

 

 

 

 

KLR1

The percentage tolerance for over-consumption of a Controllable Load Resource when the CLR has Ancillary Service responsibility

PRDE

Factor/FactorValue

KLR1_NOAS

The percentage tolerance for over-consumption of a Controllable Load Resource when the CLR does not have Ancillary Service responsibility

PRDE

Factor/FactorValue

KLR2

The percentage tolerance for under-consumption of a Controllable Load Resource when the CLR has Ancillary Service responsibility

PRDE

Factor/FactorValue

KLR2_NOAS

The percentage tolerance for under-consumption of a Controllable Load Resource when the CLR does not have Ancillary Service responsibility

PRDE

Factor/FactorValue

PRZ1

The minimum price to use for the charge calculation when the CLR over consumed

PRDE

Factor/FactorValue

PRZ2

The maximum price to use for the charge calculation when the CLR under consumed

PRDE

Factor/FactorValue

QLR1

The MW tolerance for over-consumption of a Controllable Load Resource

PRDE

Factor/FactorValue

QLR2

The MW tolerance for under-consumption of a Controllable Load Resource

PRDE

Factor/FactorValue

 

Extract Changes:

The Following table additions will be made to the Public Reference Data Extract (PRDE) and the supporting documentation for NPRR555:

·         LOADRESOURCES

·         DISPATCHTYPE

ACTION REQUIRED:  Implement changes to SCED to allow participation of Load Resources in compliance with NPRR555 and allow Load Resources to provide Non-Spin in compliance with NPRR532

ADDITIONAL INFORMATION:  Pursuant to Protocol Section 21.6, Nodal Protocol Revision Implementation, ERCOT is required to provide notice as soon as practicable, but no later than ten days prior to implementation of any NPRR that is not implemented on the first day of the month following Board approval of the NPRR.

NPRR532, NPRR555 and NPRR591 with associated documents can be found on the ERCOT website.

Information on upcoming releases can be found on the Project Priority List (PPL).

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask].