NOTICE DATE:  April 15, 2016
NOTICE TYPE:  M-A041516-01 NPRR
SHORT DESCRIPTION:  Implementation Details of NPRR719 and COPMGRR040
INTENDED AUDIENCE:  ERCOT Market Participants
DAY AFFECTED:  May 1, 2016
LONG DESCRIPTION:  On May 1, 2016, Nodal Protocol Revision Request (NPRR) 719, Removal of Trigger and Requirement to Reduce the Distributed Generation (DG) Registration Threshold, and COPMGRR040, Alignment with NPRR719, Removal of Trigger and Requirement to Reduce the Distributed Generation (DG) Registration Threshold, will be implemented.
NPRR719 was approved by the ERCOT Board on December 8, 2015 and COPMGRR040 was approved by the Technical Advisory Committee (TAC) on December 16, 2015.
NPRR719 removes the requirement for ERCOT to reduce the DG registration threshold when the aggregated unregistered installed capacity of DG greater than 50 kW in any one Load Zone reaches 10 MW. COPMGRR040 removes the inclusion of the new proposed threshold for DG registration threshold as defined in Protocol Section 16.5, Registration of a Resource Entity, in the ERCOT Unregistered Distributed Generation Report, which is published on the Market Information System (MIS) Public Area.
ADDITIONAL INFORMATION:  Pursuant to Nodal Protocol Section 21.6, Nodal Protocol Revision Implementation, ERCOT is required to provide notice as soon as practicable, but no later than ten days prior to implementation.
NPRR719<http://www.ercot.com/mktrules/issues/NPRR719> and COPMGRR040<http://www.ercot.com/mktrules/issues/COPMGRR040> and associated documents can be found on the ERCOT website.
CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask]<mailto:[log in to unmask]>.