Attached please find my first cut at the Draft PGRR for compliance with TPL-007-1 Requirement 1.

 

This document will need to receive full ERCOT internal review before being submitted to ROS and perhaps before being submitted to PLWG for approval.  Accordingly, it is being offered to you for comments before having received full ERCOT internal review, as well as in parallel to ongoing ERCOT review, so please duly note this.

I initially included dates and relative dates in this document but removed them after discussions with Mike J and while interpreting the “Guidelines for Creation/Modification of Planning Guides” to suggest that details would best be including in working group procedural documents instead of the Planning Guides (See “Guidelines for Creation/Modification of Planning Guides” http://www.ercot.com/committee/plwg ).  I subsequently submitted them without dates for a first cut review by Jeff.  Yet, Jeff’s first cut comments indicated that he felt we need the dates so I left his comments in the attached along with my responses as additional points for discussion.

 

Also, below are some potential, best case scheduling, sponsoring scenarios for comparison.  The TSP/RE sponsor for posting appears to be least likely.  And, as I understand it, since PGDTF is a task force and not a working group, PGDTF would need ROS to direct it to sponsor this PGRR creating some scheduling concerns.  Yet, I still have scheduling concerns with ERCOT sponsoring this PGRR, receiving comments from PGDTF on 1/11/17, and submitting to [log in to unmask] the next day (1/12/17), so we still need to sort through all of this and your comments would be appreciated.  The attached document is being offered to you for comments under the assumption that I will be the one to sponsor it as an ERCOT Planning Engineer.

 

 

TSP/RE sponsored:

01/10/17 – PGRR posting deadline for 1/25/17 PLWG (TSP/RE would need to send draft to [log in to unmask] asap – per Planning Guide 1.2.4.1, ERCOT would have 5 days to respond and 3 days to post after the draft is considered to be complete.)

01/11/17 – PGDTF reviews draft

01/25/17 – PLWG language review/approval

02/22/17 – PLWG IA review/approval

03/02/17 – ROS approval

03/23/17 – TAC approval

04/04/17 – Board approval

 

PGDTF sponsored:

01/10/17 – PGRR posting deadline for 1/25/17 PLWG – PGDTF will miss this, if they want to wait for group review before filing.

01/11/17 – PGDTF reviews draft

02/02/17 – ROS grants permission for PGDTF to file PGRR

02/07/17 – PGRR posting deadline for 2/22/17 PLWG

02/22/17 – PLWG language review/approval

03/22/17 – PLWG IA review/approval

04/06/17 – ROS approval

04/27/17 – TAC approval

06/13/17 – Board approval

 

ERCOT sponsored:

01/11/17 – PGDTF reviews draft

01/12/17 – ERCOT staff submits draft to [log in to unmask] for assignment to Market Rules analyst.

01/16/17 – 12noon deadline for BP agenda/packet

01/18/17 – BP reviews draft, approves concept, sends to triage for IA

02/01/17 – BP reviews IA, approves posting

02/07/17 – PGRR/IA posting deadline

02/22/17 – PLWG language review/approval

03/22/17 – PLWG IA review/approval

04/06/17 – ROS approval

04/27/17 – TAC approval

06/13/17 – Board approval

 

 

 

 

 

A. Benjamin Richardson, P.E.(Colorado)

Transmission and Interconnection Studies

2705 West Lake Drive

Taylor, TX 76574

O: 512-248-4505 | M:720-470-3643 

 

 