NOTICE DATE: January 18, 2018
NOTICE TYPE: W-A070617-04 Release - Wholesale
SHORT DESCRIPTION: Implementation details for NPRR809
INTENDED AUDIENCE: ERCOT Market Participants
DAYS AFFECTED: February 1, 2018
LONG DESCRIPTION:
ERCOT will be partially implementing Nodal Protocol Revision Request (NPRR) 809, GTC or GTL for New Generation Interconnection, on February 1, 2018.
Paragraph (4)(c) of Section 16.5, Registration of a Resource Entity requires that any
required sub-synchronous resonance studies for an All-Inclusive Generation Resource be completed and approved by ERCOT no later than 90 days prior to Initial Synchronization.
Paragraph (7) of Section 3.10.7.6, Use of Generic Transmission Constraints and Generic Transmission Limits, will be implemented at a later date.
NPRR809 was partially implemented on August 1, 2017 as described in the Market Notice below.
ADDITIONAL INFORMATION: Pursuant to Nodal Protocol Section 21.6, Nodal Protocol Revision Implementation, ERCOT is required to provide notice as soon as practicable, but no later than ten days prior to implementation.
NPRR809 and associated documents can be found on the ERCOT website.
CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email
at [log in to unmask].
If you are receiving email from a public ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe
from this list: http://lists.ercot.com.
mm
NOTICE DATE: July 31, 2017
NOTICE TYPE: W-A070617-03 Release - Wholesale
SHORT DESCRIPTION: Reminder - Implementation Details for PGRR052, PGRR054, and NPRR809
INTENDED AUDIENCE: ERCOT Market Participants
DAYS AFFECTED: August 1, 2017
LONG DESCRIPTION: ERCOT will be implementing Planning Guide Revision Request (PGRR) 052, Stability Assessment for Interconnecting Generation, and PGRR054, Stability Limits in the
Full Interconnect Study, and partially implementing Nodal Protocol Revision Request (NPRR) 809, GTC or GTL for New Generation Interconnection, on August 1, 2017. Paragraph (7) of Section 3.10.7.6, Use of Generic Transmission Constraints and Generic Transmission
Limits, and paragraph (4)(c) of Section 16.5, Registration of a Resource Entity, will be implemented at a later date.
PGRR052 establishes a timeline for performing stability studies after the Full Interconnection Study (FIS) has been completed and model data or transmission system changes, not known during the FIS, become available
prior to a new unit being brought on-line, in order to ensure that appropriate operating limits are established.
PGRR054 clarifies the content, review period and process for posting the results of an FIS, and establishes a process for identifying, proposing, and implementing solutions to stability issues identified during
the FIS.
NPRR809 establishes Initial Energization and Initial Synchronization as defined terms, changes the status of Protected Information used in an interconnection study, adds a reference to a quarterly stability assessment
for interconnecting Generation Resources when evaluating the need for a Generic Transmission Constraint (GTC), and clarifies the requirements to be met for a Generation Resource prior to Initial Synchronization.
Upon implementation, the following new portlets and links will be added to the Market Information System (MIS):
New Portlet |
Link Name |
MIS Location |
Quarterly Stability Assessments |
Quarterly Stability Assessments |
Grid > Resource Integration |
Final Full Interconnection Study Reports and Other Information |
Final Full Interconnection Study Reports and Other Information |
Grid > Resource Integration |
GINR Archives |
GINR Archives The following existing portlets will be moved to this link: * Partial Generation Interconnection (INR) Studies (Secure) * TSP Generation Interconnection (INR) Studies (Certified) |
Grid > Resource Integration |
Certified Interconnection Study Documents: Inputs, Draft Reports, and SSR Studies |
Certified Interconnection Study Documents: Inputs, Draft Reports, and SSR Studies |
Grid > Resource Integration |
In addition, the Certified link to
Signed Generation Interconnection Agreements (SGIA) (NP1-321-M, Report ID 13260) on the Grid > Resource Integration page will be removed.
ADDITIONAL INFORMATION:
PGRR052,
PGRR054, and NPRR809 and associated documents can be found on the ERCOT website.
CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT
Client Services via email at [log in to unmask].
If you are receiving email from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list:
http://lists.ercot.com.
CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT
Client Services via email at [log in to unmask].
If you are receiving email from a public ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this
list: http://lists.ercot.com.
sa