***** EXTERNAL email. Please be cautious and evaluate before you click on links, open attachments, or provide credentials. *****

NOTICE DATE:  April 9, 2018

NOTICE TYPE:  W-A040918-01 Operations

SHORT DESCRIPTION:  Commissioning of Tule Canyon Synchronous Condenser

INTENDED AUDIENCE:  ERCOT Market Participants

DAY AFFECTED:  April 9, 2018

LONG DESCRIPTION:  Sharyland Utilities has completed its initial tuning for the synchronous condenser at the Tule Canyon substation.  The synchronous condenser will be placed in service for continual operation on April 9, 2018.  At that time, ERCOT will begin considering the synchronous condenser in its calculation of limits for the Panhandle Generic Transmission Constraint (GTC).  The purpose of this notice is to provide contemporaneous notification to all ERCOT Market Participants of the topology change in the Panhandle, as it may have an impact on the limits associated with the Panhandle GTC.

Details associated with all existing GTCs can be found on the ERCOT MIS Secure Area in the “Generic Transmission Constraints” portlet.  A Digital Certificate is required to access the MIS Secure Area.

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask].

If you are receiving email from a public ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.

 

 

 

sa/mm