NOTICE DATE:  August 20, 2018

NOTICE TYPE:  W-A082018-01 Settlements

SHORT DESCRIPTION:  Settlement for the ERS Standard Contract Term of October 1, 2017 through January 31, 2018

INTENDED AUDIENCE:  QSE settlement personnel

DAY AFFECTED:  October 1, 2017 through January 31, 2018 – ERS Standard Contract Term

LONG DESCRIPTION:  The October 1, 2017 through January 31, 2018, Emergency Response Service (ERS) Standard Contract Term will be settled on the True-Up Settlement Statement of Operating Day February 20, 2018.

 

The payments for ERS-10 for the October 1, 2017 through January 31, 2018, ERS Standard Contract Term are as follows:

 

Time Period

ERS Payments

Time Period 1 (HE 0600-0800)*

ERSPAMTTOT_1_10

$877,131.68

Time Period 2 (HE 0900-1300)*

ERSPAMTTOT_2_10

$556,330.67

Time Period 3 (HE 1400-1600)*

ERSPAMTTOT_3_10

$114,481.57

Time Period 4 (HE 1700-1900)*

ERSPAMTTOT_4_10

$874,654.00

Time Period 5 (HE 2000-2200)*

ERSPAMTTOT_5_10

$912,133.70

Time Period 6 (All other hours)

ERSPAMTTOT_6_10

$744,007.39

TOTAL for Contract Period

$4,078,739.01

* Monday through Friday except ERCOT Holidays

 


The payments for ERS-30 for the October 1, 2017 through January 31, 2018, ERS Standard Contract Term are as follows:

 

Time Period

ERS Payments

Time Period 1 (HE 0600-0800)*

ERSPAMTTOT_1_30

$2,663,860.89

Time Period 2 (HE 0900-1300)*

ERSPAMTTOT_2_30

$1,709,890.39

Time Period 3 (HE 1400-1600)*

ERSPAMTTOT_3_30

$347,015.57

Time Period 4 (HE 1700-1900)*

ERSPAMTTOT_4_30

$2,687,376.18

Time Period 5 (HE 2000-2200)*

ERSPAMTTOT_5_30

$2,757,683.41

Time Period 6 (All other hours)

ERSPAMTTOT_6_30

$2,119,838.31

TOTAL for Contract Period

$12,285,664.75

* Monday through Friday except ERCOT Holidays

 

The payments for ERS-30 Weather Sensitive for the October 1, 2017 through January 31, 2018, ERS Standard Contract Term are as follows:

 

Time Period

ERS Payments

Time Period 1 (HE 0600-0800)*

ERSPAMTTOT_1_30_WS

$18,201.90

Time Period 3 (HE 1400-1600)*

ERSPAMTTOT_3_30_WS

$1,591.09

Time Period 4 (HE 1700-1900)*

ERSPAMTTOT_4_30_WS

$17,797.87

TOTAL for Contract Period

$37,590.86

* Monday through Friday except ERCOT Holidays

 


Pursuant to Protocols Section 6.6.11.2(1), “For the first settlement of the ERS Contract Period as described in paragraph (1) of Section 9.14.5, Settlement of Emergency Response Service, LRS will be calculated using the latest Settlement Load for each Operating Day in the ERS Contract Period.”

 

The latest Settlement Load used to calculate True-Up ERS charges for the October 1, 2017 through January 31, 2018, ERS Standard Contract Term is as follows:

 

Time Period

RTAML Total

Time Period 1 (HE 0600-0800)*

9,895,759.9891810 MWh

Time Period 2 (HE 0900-1300)*

17,389,635.4946540 MWh

Time Period 3 (HE 1400-1600)*

10,475,485.5116920 MWh

Time Period 4 (HE 1700-1900)*

10,779,947.9571690 MWh

Time Period 5 (HE 2000-2200)*

10,741,879.0446710 MWh

Time Period 6 (All other hours)

57,015,374.3396070 MWh

RTAML Total used for Contract Period

116,298,082.3369740 MWh

* Monday through Friday except ERCOT Holidays

 

Pursuant to Protocols Section 9.14.5(1), “All disputes for the Settlement of the ERS Contract Period are due ten Business Days after the date that the ERS settlement was posted. ERCOT shall resolve any approved disputes upon resettlement of the ERS Contract Period, as described in Section 9.14.5(2).”

 

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask].