PGDTF,

The materials for Pass 5 of the GIC Model Build have been posted to MIS. For this pass, make any final corrections or fixes you think are necessary to your equipment in the model. Pass 5 is the final pass of the GIC System Model Build. If you have no changes to submit and have no issues with the model, please confirm so otherwise submit changes.

As of 6/14/2019, ERCOT is no longer accepting any changes to generation in the case. This includes both new announced retirements and new generation that meets 6.9(2). Major topology changes will also not be accepted. However minor changes to correct issues with the model are acceptable. Our goal is to have the model finalized and ready at the end of Pass Five.

The several outstanding issues are:

*         Review the Full Database Validation log for any of your elements and double check the data. Just because something has been flagged does not mean it is wrong. However if it is incorrect, make a submission to modify the DC Model.

*         Review all of your transformer vector groups to ensure that the vector group is in the I/J/K bus order and not ordered High/Low (unless the I/J bus order is High/Low). I'd recommend either filtering by your bus range and exclude any transformers with a blank JobId (a blank JobId means no change has been made to that transformer through the entire model build. It also was not impacted by the RAW file imports) or sort for JobId of: 102, 104 (102 and 104 are the RAW file imports), and any associated with your submissions (the association of JobIds and submissions can be found in the Job Log excel file). If you need to change a vector group, make a submission using the DC template.

*         Review the transformers with zero flows and are in your bus range. If you find a modeling issue, make a submission to correct for it.

*         Case Conditioning - Review the AC Model without the DC Model and ensure that all the voltages are within the limits you'd expect for your area. Submit an Idev if you need to adjust voltages.

Reminder: Make all submissions to [log in to unmask]<mailto:[log in to unmask]>.

Pass 5 End Date: 7/5/2019


[cid:image001.png@01D5285A.B74FDDD0]


If you have any questions please call or email me.

Thanks,

Eric


[cid:image001.jpg@01D16FE2.A112C930]<http://www.ercot.com/>


Eric Meier
Network Model Engineer 2
Network Model Administration
2705 West Lake Drive
Taylor, Texas 76574
[log in to unmask]<mailto:[log in to unmask]>
O: 512-248-6770




########################################################################

To unsubscribe from the PGDTF list, click the following link:
http://lists.ercot.com/scripts/wa-ERCOT.exe?SUBED1=PGDTF&A=1