Hi Everyone,

 

Based on my discussions with ERCOT, I’ve revised my proposal language and presentation (both attached) on maintaining Participation Factors as an option that should work well with RTC. The following is a description of the proposal:

  1. RTC and LFC would function exactly as described in the ERCOT proposal.
  2. QSEs have the option of telemetering PFs – for all QSEs not exercising this option, there is no change to the ERCOT proposal.
  3. For QSEs that telemeter PFs, since there is a 8-45 second communication delay in ERCOT accepting telemetered PFs after each RTC run that are aligned with the RTC awards, the first few LFC cycles after each RTC run until aligned PFs are accepted by ERCOT, the QSE resources will be deployed and performance measured based on the exact LFC deployment (as in the ERCOT proposal).
  4. Once the aligned PFs have been accepted by ERCOT after each RTC run and until the next RTC run, real-time resource performance monitoring, GREDP, Base Point Deviation, etc. will all be measured using LFC deployments adjusted for telemetered PFs.

 

Please post these instead of previous documents on PFs. I look forward to discussing these at RTCTF.

 

Regards,

Shams Siddiqi, PhD

President, Crescent Power, Inc.

11412 Bee Caves Rd, Suite 202

Austin, Texas 78738

Tel. +1.512.619.3532

Email: [log in to unmask]

www.crescentpower.net

 

 

 

From: [log in to unmask] <[log in to unmask]>
Sent: Monday, July 8, 2019 3:06 PM
To: 'Mereness, Matt' <[log in to unmask]>; [log in to unmask] <[log in to unmask]>
Subject: RE: July 12 RTCTF Agenda and materials posted

 

Hi Everyone,

 

Attached are my presentations on maintaining Participation Factors in LFC and AS Demand Curve Capability in RUC for RTCTF on 7/12/19.

 

Let me know if you have any questions.

 

Regards,

Shams Siddiqi, PhD

President, Crescent Power, Inc.

11412 Bee Caves Rd, Suite 202

Austin, Texas 78738

Tel. +1.512.619.3532

Email: [log in to unmask]

www.crescentpower.net

 

 

 

From: Mereness, Matt <[log in to unmask]>
Sent: Monday, July 1, 2019 1:29 PM
To: [log in to unmask]
Subject: July 12 RTCTF Agenda and materials posted

 


***** EXTERNAL email. Please be cautious and evaluate before you click on links, open attachments, or provide credentials. *****

Good afternoon RTCTF members,

ERCOT has posted the agenda and materials for the July 12 RTCTF meeting to be hosted at the Taylor ERCOT control center.

                http://www.ercot.com/calendar/2019/6/21/180300-RTCTF  (please RSVP by 12NOON on 7/10/19 if you plan to attend in person)

 

It’s a full agenda, and materials for Agenda 4 are posted for comment in anticipation of taking a number of items to the July TAC meeting.  Please provide any alternatives language for items below by close of business July 5, 2019:

 

Thanks,

Matt

 

Matt Mereness

[log in to unmask]

O: 512.248.3089

M: 512.565.8939

 

 

 


To unsubscribe from the RTCTF list, click the following link:
http://lists.ercot.com/scripts/wa-ERCOT.exe?SUBED1=RTCTF&A=1



To unsubscribe from the RTCTF list, click the following link:
http://lists.ercot.com/scripts/wa-ERCOT.exe?SUBED1=RTCTF&A=1