Hi Everyone,

 

Attached is my presentation on KP1.1 Real-Time AS Demand Curves for RTCTF meeting on 9/19/19.

 

I look forward to discussing this at the meeting.

 

Regards,

Shams Siddiqi, PhD

President, Crescent Power, Inc.

11412 Bee Caves Rd, Suite 202

Austin, Texas 78738

Tel. +1.512.619.3532

Email: [log in to unmask]

www.crescentpower.net

 

 

 

From: Mereness, Matt <[log in to unmask]>
Sent: Friday, September 13, 2019 11:45 AM
To: [log in to unmask]
Subject: RTCTF Sep 19 meeting materials posted

 


***** EXTERNAL email. Please be cautious and evaluate before you click on links, open attachments, or provide credentials. *****

RTCTF,

ERCOT and market comments have been posted for the Sept 19th meeting and it will be a full day.  I wanted to highlight the input received and posted on each of these topics below.  (http://www.ercot.com/calendar/2019/9/19/180276-RTCTF)

 

KP1.1 - Curve Disaggregation into Individual ASDC

KP1.2 - KP1.2 - Capping of MCPCs when Energy Price is Capped

KP 1.3 - RTC Constraints

KP 5 - Day-Ahead Market

KP 2- Definition of AS Products to align with RTC Framework

 

Thank you for the continued support,

Matt

 

From: Mereness, Matt
Sent: Tuesday, September 10, 2019 2:13 PM
To: [log in to unmask]
Subject: RE: RTCTF Posting for Sept 19 Meeting (comments due Sep 12)

 

RTCTF,

A reminder that comments/alternatives are due Thursday Sept 12th (a week ahead of the Sept 19 meeting).

Thanks,

Matt

 

Matt Mereness

[log in to unmask]

O: 512.248.3089

M: 512.565.8939

 

From: Mereness, Matt
Sent: Friday, August 30, 2019 1:16 PM
To: [log in to unmask]
Subject: RTCTF Posting for Sept 19 Meeting (comments due Sep 12)

 

RTCTF,

ERCOT has posted the updated Key Principle documents with revisions for the next meeting on Sep 19th (http://www.ercot.com/calendar/2019/9/19/180276-RTCTF).  Below is a rather long summary of the expectations for each of these items, and reminder that comments/alternative are due a week ahead of time, Thursday Sept 12.

 

KP 1.1 AS Demand Curves (2) and (5)-

Sep 19th meeting will be the final RTCTF consideration of this item.

 

KP 1.2 System-Wide Offer Cap and Power Balance Penalty Price (3)-      

      Sep 19th meeting will be second meeting to review potential options for AS Price Caps (MPs need to bring comments/language/options).

 

KP 1.3 Offering and Awarding AS in Real-Time (1)-(12)-

      Sep 19th meeting will be an extra meeting to further understand and review potential options (MPs need to bring comments/language/options).

 

KP 5 Day-Ahead Market (1)-(6)

      Sep 19th meeting will be second meeting on DAM changes

 

Your time and energy are appreciated and ERCOT staff are available to support questions/details on these items,

Matt

 

Matt Mereness

[log in to unmask]

O: 512.248.3089

M: 512.565.8939

 

 

 

 

 


To unsubscribe from the RTCTF list, click the following link:
http://lists.ercot.com/scripts/wa-ERCOT.exe?SUBED1=RTCTF&A=1



To unsubscribe from the RTCTF list, click the following link:
http://lists.ercot.com/scripts/wa-ERCOT.exe?SUBED1=RTCTF&A=1