NOTICE DATE: August 18, 2022

NOTICE TYPE: M-E121721-02 Operations

SHORT DESCRIPTION:  Reminder for Submission of Plant Verification Reports

INTENDED AUDIENCE:  Resource Entities

DAY AFFECTED:  March 1, 2023

LONG DESCRIPTION:  Pursuant to PGRR085 approved on February 9, 2021 and ERCOT Planning Guide Section 5.5(3)(b)(ii), the Resource Entities for all Generation Resources and Energy Storage Resources shall provide ERCOT with a plant verification report no earlier than 12 months and no later than 24 months following the later of Resource Commissioning Date or March 1, 2021, as required by paragraph (5)(b) of Planning Guide Section 6.2.

All Generation Resources and Energy Storage Resources in-service before March 1, 2021, must submit the required information by March 1, 2023.

ERCOT requests that Resource Entities who have not already submitted the model verification reports submit the required information to the online Resource Integration and Ongoing Operations Resource Services (RIOO-RS) system.

ADDITIONAL INFORMATION:  The Verification report is different from the NERC MOD-026/027 reports. 

Helpful instruction can be found in the Model Quality Guide posted under the Guides section of the Resource Entities page on the ERCOT website.   After downloading this zip file, please review the “About Verification Reports” document.

Please review the ERCOT website for previous Market Notices and Rules related to this subject. 

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask].

If you are receiving email from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.

 