ERCOT Client Services <[log in to unmask]>
Date:
Fri, 27 Jun 2014 15:30:08 +0000
Content-Type:
multipart/alternative
Parts/Attachments:
text/plain (2748 bytes) , text/HTML (46 kB)
***** EXTERNAL email. Please be cautious and evaluate before you click on links, open attachments, or provide credentials. *****

NOTICE DATE:  June 27, 2014
NOTICE TYPE:  W-A052214-02 Operations
SHORT DESCRIPTION:  Corrections to the assignments of Loads to NOIE and Competitive Load Zones in the Network Operations Model
INTENDED AUDIENCE:  ERCOT Market Participants
DAY AFFECTED:  Various Operating Days since Nodal Go-Live through July 8, 2014
LONG DESCRIPTION:  The table below lists corrections to the assignments of Loads to Non-Opt-In Entity (NOIE) and Competitive Load Zones. These Loads listed below are in addition to the Loads identified in Market Notice W-A052214-01, issued on May 22.  The total of these Load quantities that were assigned incorrectly to a Load Zone is 65 MW based on the current hot weather Load distribution factors but will vary by the hour and season.

These corrections will have an effective date of July 9, 2014 to coincide with an update to the Network Operations Model.

Individual Load to Load Zone Assignment

Station

Load

Original Load Zone

Corrected Load Zone

ANTLER

T1

LZ_SOUTH

LZ_LCRA

AVERRA

AVERRAT3

LZ_SOUTH

LZ_LCRA

ESCARP

ESCARP_T_1

LZ_SOUTH

LZ_LCRA

FERGCC

1EX-TF-A

LZ_SOUTH

LZ_LCRA

FERGCC

1EX-TF-B

LZ_SOUTH

LZ_LCRA

FLATON

FLATONT4

LZ_LCRA

LZ_SOUTH

GIDEON

GIDEON1&2

LZ_SOUTH

LZ_LCRA

GIDEON

GIDEON3&4

LZ_SOUTH

LZ_LCRA

MANCHA

MANCHAT2

LZ_SOUTH

LZ_LCRA

MARBFA

MFL_SS1XFMR

LZ_SOUTH

LZ_LCRA

MARBFA

MFL_SS2XFMR

LZ_SOUTH

LZ_LCRA

MARSFO

MFD_SS1XFMR

LZ_SOUTH

LZ_AEN

MARSFO

MFD_SS3XFMR

LZ_SOUTH

LZ_AEN

SPICEW

SPICEWT2

LZ_SOUTH

LZ_LCRA

WELFAR

WELFART1

LZ_SOUTH

LZ_LCRA

WIPOPA

AUX_12

LZ_SOUTH

LZ_LCRA

WIPOPA

AUX_34

LZ_SOUTH

LZ_LCRA

WIRTZ

WIR_FLGXFMR

LZ_SOUTH

LZ_LCRA

WIRTZ

WIR_SS1XFMR

LZ_SOUTH

LZ_LCRA

WIRTZ

WIR_SS2XFMR

LZ_SOUTH

LZ_LCRA


The incorrect Load to Load Zone assignments impacted the results of the price calculations for the Day-Ahead Market (DAM) and Real-Time Market (RTM) and flow calculations for the Congestion Revenue Right (CRR) Auctions and the DAM for some intervals since Nodal Go-Live.  However, ERCOT will not perform any price corrections because the error does not meet the criteria described in Protocol Sections 4.5.3(4) and 6.3(4).  Lastly, the incorrect assignments of Loads to NOIE and Competitive Load Zones did not have an impact on the MWh quantities allocated to NOIE Load Zones for energy Settlements.

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask]<mailto:[log in to unmask]>.