NOTICE_OPERATIONS Archives

Notice_Operations

NOTICE_OPERATIONS@LISTS.ERCOT.COM

Options: Use Forum View

Use Monospaced Font
Show HTML Part by Default
Show All Mail Headers

Message: [<< First] [< Prev] [Next >] [Last >>]
Topic: [<< First] [< Prev] [Next >] [Last >>]
Author: [<< First] [< Prev] [Next >] [Last >>]

Print Reply
Subject:
From:
ERCOT Client Services <[log in to unmask]>
Date:
Thu, 24 Aug 2017 21:52:31 +0000
Content-Type:
multipart/alternative
Parts/Attachments:
text/plain (5 kB) , text/html (11 kB)
***** EXTERNAL email. Please be cautious and evaluate before you click on links, open attachments, or provide credentials. *****

NOTICE DATE:  August 24, 2017

NOTICE TYPE:  W-A041516-03 Operations

SHORT DESCRIPTION:  Update - Potential for a Lobo – North Edinburg Generic Transmission Constraint

INTENDED AUDIENCE:  ERCOT Market Participants

DAY AFFECTED:  August 24, 2017

LONG DESCRIPTION:  On October 5, 2016, the Pomelo Generic Transmission Constraint (GTC) began being enforced.  This GTC has been needed to resolve local area instability issues associated with existing and planned Generation Resources in the Pomelo area.  Since the implementation of this GTC, ERCOT has performed additional assessments using updated network models. These additional assessments have concluded that the GTC needs to be expanded and the limits associated with the GTC be revised.

To address this, ERCOT is replacing the Pomelo GTC with a new GTC named “North Edinburg – Lobo.”  ERCOT will begin enforcing the North Edinburg – Lobo GTC on August 24, 2017.

The purpose of this notice is to provide contemporaneous notification to all ERCOT Market Participants about these changes.  ERCOT will cease posting limits for the Pomelo GTC, and begin posting limits for the North Edinburg – Lobo GTC.

Details associated with all existing GTCs can be found on the ERCOT MIS Secure Area in the “Generic Transmission Constraints” portlet.  A Digital Certificate is required to access the MIS Secure Area.

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask]<mailto:[log in to unmask]>.





sa

________________________________________________________________

NOTICE DATE: September 22, 2016

NOTICE TYPE:  W-A041516-02 Operations

SHORT DESCRIPTION: Potential Need for a Lobo – North Edinburgh Generic Transmission Constraint

INTENDED AUDIENCE:  ERCOT Market Participants

DAY AFFECTED:  October 5, 2016

LONG DESCRIPTION:  On April 15, 2016, ERCOT issued Market Notice W-A041516-01 indicating the potential need for a Generic Transmission Constraint (GTC) near the Lobo – North Edinburgh 345 kV line.  ERCOT indicated that the potential GTC would be established to address instability issues with existing and planned Generation Resources in the area.  ERCOT has completed this assessment and has determined that a GTC is needed to manage local voltage stability and low short circuit current issues in the area.

The purpose of this notice is to provide contemporaneous notification to all ERCOT Market Participants of the need for the GTC.  ERCOT will begin enforcing limits for this GTC—which will be called the “Pomelo GTC”—on October 5, 2016.

It is important to note that additional assessments about the stability of this area are still under study.  This GTC and its parameters may change as those additional assessments are completed and reviewed.  In the event changes are needed, ERCOT will notify the market as appropriate.

Details associated with the Pomelo GTC and all other existing GTCs can be found on the ERCOT MIS Secure Area in the “Generic Transmission Constraints” portlet.  A Digital Certificate is required to access the MIS Secure Area.

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask]<mailto:[log in to unmask]>.

If you are receiving email from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.







nb

NOTICE DATE:  April 15, 2016

NOTICE TYPE:  W-A041516-01 Operations

SHORT DESCRIPTION:  Potential Need for a Lobo – North Edinburgh Generic Transmission Constraint

INTENDED AUDIENCE:  ERCOT Market Participants

DAY AFFECTED:  Expected October 2016

LONG DESCRIPTION:  A Full Interconnection Study (FIS) completed by AEP Texas Central Company for a proposed Generating Resource indicates that ERCOT may need to create a Generic Transmission Constraint (GTC) near the Lobo – North Edinburgh 345 kV line after this line is commissioned and the proposed Generation Resource is synchronized.  The potential GTC would be established to address instability issues with existing and planned Generation Resources in the area.

The purpose of this notice is to provide notification to all ERCOT Market Participants about the potential need for the new GTC.  No details associated with this potential GTC are available at this time as ERCOT has not completed its own study which would include the determination of how the potential GTC would be defined.  In the event a GTC is defined, ERCOT will provide that information on the MIS Secure Area.

Details associated with all existing GTCs can be found on the ERCOT Market Information System (MIS) Secure Area in the “Generic Transmission Constraints” portlet.  A Digital Certificate is required to access the MIS Secure Area.

CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask]<mailto:[log in to unmask]>.