NOTICE DATE: May 25, 2016
NOTICE TYPE: W-A051316-03 Operations
SHORT DESCRIPTION: Testing of Series Capacitors on new Lobo to North Edinburg 345 kV Transmission Line is complete
INTENDED AUDIENCE: ERCOT Market Participants
DAY AFFECTED: May 25, 2016
LONG DESCRIPTION: AEP Texas Central Company has completed testing of the series capacitors located at the Cenizo and Del Sol substations on the new Lobo to North Edinburg 345 kV Transmission Line.
These series capacitors will remain bypassed until further notice.
CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask]<mailto:[log in to unmask]>.
If you are receiving email from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list: http://lists.ercot.com.
sa