NOTICE DATE:  March 2, 2016
NOTICE TYPE:  W-A030216-01 Operations
SHORT DESCRIPTION:  Proposal to model Special Protection System at Javelina Wind Energy Project
INTENDED AUDIENCE:  ERCOT Market Participants
DAY AFFECTED:  Comments due March 15, 2016

LONG DESCRIPTION:  ERCOT has received a proposal from Nextera Energy Power Marketing LLC (Nextera) to model a generator control algorithm implemented in the wind turbines at Javelina Wind Energy Project (Javelina) as a Special Protection System (SPS). The Javelina SPS is designed to mitigate potential control instabilities that may occur in the region under various system conditions.



In accordance with the guidance outlined in Nodal Operating Guide 11.2(3)(b)<http://www.ercot.com/mktrules/guides/noperating/cur>, the Javelina SPS generator control algorithm has been in-service since January 11, 2016. This SPS is expected to be retired when the Javelina Wind Energy Project Point of Interconnection (POI) changes to 345 kV (via Lobo - Zapata 345 kV line) from its current 138 kV POI.


The proposal to model the Javelina SPS is being reviewed by ERCOT. Comments on the proposal are due by March 15, 2016 and should be submitted to [log in to unmask]<mailto:[log in to unmask]>  using the attached comment form.  Any questions or concerns submitted by this date will be addressed by ERCOT, Nextera and/or the interconnecting Transmission Operator.
ACTION REQUIRED:  Any comments to this proposal are due to ERCOT by March 15, 2016, using the attached form.
ADDITIONAL INFORMATION:  Information regarding this proposal and all SPSs can be found in the "Special Protection Systems and Remedial Action Plans" portlet located on the Long-Term Planning<https://mis.ercot.com/pps/tibco/mis/Pages/Grid+Information/Long+Term+Planning> page of ERCOT's Market Information System (MIS). A Digital Certificate is required to access the MIS.
CONTACT:  If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask]<mailto:[log in to unmask]>.