NOTICE DATE: January 5, 2011
NOTICE TYPE: M-D010511-01 NPRR/SCR
SHORT DESCRIPTION: Implementation of NPRR278, Emergency Interruptible Load Service (EILS) Modifications to Correct Self-Provision Settlement Equations, to Accommodate Advanced Metering Infrastructure, and other Clarifications, and additional Nodal Protocol sections related to EILS.
INTENDED AUDIENCE: QSEs
DAY AFFECTED: February 1, 2011
LONG DESCRIPTION: The ERCOT Board of Directors approved NPRR278, Emergency Interruptible Load Service (EILS) Modifications to Correct Self-Provision Settlement Equations, to Accommodate Advanced Metering Infrastructure, and other Clarifications, on November 16, 2010. NPRR278 and additional Nodal Protocol sections related to EILS were grey-boxed in the December 1, 2010 Nodal Protocols. The NPRR and EILS sections have a designated effective date of February 1, 2011, correlating to the beginning of the February-May 2011 EILS Contract Period. Accordingly, ERCOT will un-box the following Nodal Protocol Sections effective February 1, 2011:
3.14.3, Emergency Interruptible Load Service (EILS)
6.6.11.1, EILS Capacity Payments
6.6.11.2, EILS Capacity Charge
8.1.3.1, Performance Criteria for EILS Loads
8.1.3.2, Testing of EILS Loads
8.1.3.3, Suspension of Qualification of EILS Loads and/or their QSEs
8.1.3.3.1, Performance Criteria for EILS QSEs
9.14.5, Settlement of Emergency Interruptible Load Service (EILS)
ADDITIONAL INFORMATION: The NPRR and associated documents can be found on the ERCOT website, under Market Rules, at:
http://www.ercot.com/mktrules/issues/nprr/276-300/278/index
CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask]<mailto:[log in to unmask]>.