NOTICE DATE: October 7, 2013
NOTICE TYPE: W-A090613-02 Operations
SHORT DESCRIPTION: REMINDER - The ERCOT MOTE will be open for DST testing
INTENDED AUDIENCE: QSE operations personnel
DAYS AFFECTED: See table below
LONG DESCRIPTION: The ERCOT Market Operations Test Environment (MOTE) will be available for Market Participant Daylight Saving Time (DST) testing for the two periods listed in the table below. Each testing period will be from Tuesday through Friday and will follow the simulated times shown in the table.
MOTE DST Testing
Iteration 1
Real-time
Simulated time
09/23/2013 10:00 am
10/31/2013 10:00 pm
MOTE Servers Normal Time change to DST Time
09/23/2013 01:00 pm
11/01/2013 01:00 am
Start testing QSE submissions for next 7 days including 11/02/2013, Long Day 11/03/2013 Operating Days
09/23/2013 10:00 pm
11/01/2013 10:00 am
DAM close for Operating Day 11/02/2013
09/24/2013 10:00 pm
11/02/2013 10:00 am
DAM close for Operating Day 11/03/2013 (Long DST Day )
09/25/2013 02:00 pm
11/03/2013 02:00 am
DST Transition Time
09/25/2013 03:00 pm
11/03/2013 02:00* am
DST Repeated Hour
09/25/2013 11:00 pm
11/03/2013 10:00 am
DAM close for Operating Day 11/04/2013
09/26/2013 11:00 pm
11/04/2013 10:00 am
DAM close for Operating Day 11/05/2013
09/27/2013 10:00 am
11/04/2013 09:00 pm
Close of Test and MOTE Servers DST Time Change to Normal Time
Iteration 2
Real-time
Simulated time
10/07/2013 10:00 am
10/31/2013 10:00 pm
MOTE Servers Normal Time change to DST Time
10/07/2013 01:00 pm
11/01/2013 01:00 am
Start testing QSE submissions for next 7 days including 11/02/2013, Long Day 11/03/2013 Operating Days
10/07/2013 10:00 pm
11/01/2013 10:00 am
DAM close for Operating Day 11/02/2013
10/08/2013 10:00 pm
11/02/2013 10:00 am
DAM close for Operating Day 11/03/2013 (Long DST Day )
10/09/2013 02:00 pm
11/03/2013 02:00 am
DST Transition Time
10/09/2013 03:00 pm
11/03/2013 02:00* am
DST Repeated Hour
10/09/2013 11:00 pm
11/03/2013 10:00 am
DAM close for Operating Day 11/04/2013
10/10/2013 11:00 pm
11/04/2013 10:00 am
DAM close for Operating Day 11/05/2013
10/11/2013 10:00 am
11/04/2013 09:00 pm
Close of Test and MOTE Servers DST Time Change to Normal Time
ADDITIONAL INFORMATION: For information regarding submissions, including Daylight Saving Time requirements, please refer to the latest version of the EIP External Interface Specifications document for use of the External Web Services (EWS) found in the Wholesale section of the http://www.ercot.com/services/mdt/xsds/ webpage. The most recent External Web Services XSD may also be found in the same location.
During testing, the URL for XML submissions will be: https://testingapi.ercot.com/2007-08/Nodal/eEDS/EWS/.
The URL for UI submissions will be: https://testing.ercot.com/mmsui/mmsui/displayTradesLanding.action.
The following are examples of how the Long DST Day November 3, 2013 are labeled:
0100
0200 (Normal Hour)
0200* (Repeated Hour)
0300
0400
0500.
The MOTE MPIM application will be unavailable for the duration of the DST testing.
CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-3900 or contact ERCOT Client Services via email at [log in to unmask]<mailto:[log in to unmask]>.